PRJ-2026-015On track4ExecutionScrumIn progressDelivered by:Ministry of Communications and Information Technology

Government Services Mobile App — New Release

Add to watchlist

The new release of the government services app: the most-used services, request tracking, notifications and bank e-payment.

Budget (BAC)

SYP 315M

Actual cost

SYP 193.8M

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 302.9M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

Government Services Mobile App — New Release

PRJ-2026-015 · Local Development & Governorates Sector · Strategic · WP-2025-015

In progressOn track4ExecutionProject manager: Kinan Azzam · Sponsor: Eng. Khaled Al-Kayyali
Progress
⁦64%⁩ / ⁦63%⁩
SPI · CPI
1.02 · 1.04
Spend
SYP 193.8M / SYP 315M
Estimate at completion
SYP 302.9M

Schedule

⁦1%⁩ ahead⁦64%⁩

Planned to date ⁦63%⁩

Forecast finish: 2027-01-28 · On time

SPI1.02Schedule performance index · 1.02CPI1.04Cost performance index · 1.04

Health dimensions

On track

Last update: 2026-10-26 · Up to date

Deliverables

⁦6⁩ of ⁦8⁩ due deliverables accepted on time (⁦75%⁩)

Next milestones

  • Build complete2026-11-11
  • Testing & acceptance complete2026-12-19
  • Final handover2027-01-31

Top risks

  • None

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SYP 315M: 1 on track and 0 red or critical. Weighted progress is 64% against 63% planned, spend SYP 193.8M, and EAC SYP 302.9M (SYP 12.1M under).

No project is more than a month behind baseline.