Project status card
28 October 2026
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals
PRJ-2026-013 · Development Projects Follow-up Sector · Operational · Outside the plan
- Progress
- 79% / 90%
- SPI · CPI
- 0.88 · 0.94
- Spend
- SYP 1.6B / SYP 1.9B
- Estimate at completion
- SYP 2B
Schedule
Planned to date 90%
Forecast finish: 2026-12-15 · 45 days late
SPI0.88Schedule performance index · 0.88CPI0.94Cost performance index · 0.94Health dimensions
Last update: 2026-09-14 · Update overdue
Deliverables
6 of 11 due deliverables accepted on time (55%)
Next milestones
- Testing & acceptance complete2026-12-22
- Final handover2027-01-11
Top risks
- Late link-up of the Daraa traffic control room with the smart signals12
- Quantity gaps in lighting poles and cameras between drawings and site9
Open impediments
- Progress reports not updated for 6 weeks · Overdue
Decisions and changes waiting
- Chase the data update on the southern M5 project
Copilot summary
The scope holds 1 project with a budget of SYP 1.85bn: 0 on track and 0 red or critical. Weighted progress is 79% against 90% planned, spend SYP 1.55bn, and EAC SYP 1.97bn (SYP 118.1M over).
1 project is more than a month behind baseline; the worst: Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals (45 days).