PRJ-2026-013At risk4ExecutionConstructionIn progressDelivered by:Ministry of Transport

Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals

Add to watchlist

Solar lighting for the highway between As-Sanamayn and Daraa: 1,200 lighting poles and traffic cameras, smart signals at the junctions and a traffic control room in Daraa.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 1.9B

Actual cost

SYP 1.6B

⁦84%⁩ of budget

Progress

⁦79%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 2B

+SYP 118.1M

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure11 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals

PRJ-2026-013 · Development Projects Follow-up Sector · Operational · Outside the plan

In progressAt risk4ExecutionProject manager: Eng. Maher Al-Hamawi · Sponsor: Salma Al-Zaim
Progress
⁦79%⁩ / ⁦90%⁩
SPI · CPI
0.88 · 0.94
Spend
SYP 1.6B / SYP 1.9B
Estimate at completion
SYP 2B

Schedule

⁦11%⁩ behind⁦79%⁩

Planned to date ⁦90%⁩

Forecast finish: 2026-12-15 · 45 days late

SPI0.88Schedule performance index · 0.88CPI0.94Cost performance index · 0.94

Health dimensions

At risk

Last update: 2026-09-14 · Update overdue

Deliverables

⁦6⁩ of ⁦11⁩ due deliverables accepted on time (⁦55%⁩)

Next milestones

  • Testing & acceptance complete2026-12-22
  • Final handover2027-01-11

Top risks

  • Late link-up of the Daraa traffic control room with the smart signals12
  • Quantity gaps in lighting poles and cameras between drawings and site9

Open impediments

  • Progress reports not updated for 6 weeks · Overdue

Decisions and changes waiting

  • Chase the data update on the southern M5 project

Copilot summary

The scope holds 1 project with a budget of SYP 1.85bn: 0 on track and 0 red or critical. Weighted progress is 79% against 90% planned, spend SYP 1.55bn, and EAC SYP 1.97bn (SYP 118.1M over).

1 project is more than a month behind baseline; the worst: Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals (45 days).

Planning and Statistics Authority · prepared by Eng. Maher Al-Hamawi in MunjazInternal

Status: At risk ·Project page