PRJ-2026-008On track4ExecutionScrumIn progressDelivered by:Ministry of Justice

e-Litigation & Judicial Notification Platform — Release 2

Add to watchlist

Release 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.

Budget (BAC)

SYP 460M

Actual cost

SYP 410.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SYP 451M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-10-06⁩
ApprovedDMD-2026-008e-Litigation & Judicial Notification Platform — Release 2

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-008
Project
e-Litigation & Judicial Notification Platform — Release 2
Portfolio
Digital Government Services & Data Portfolio
Sector
Legal Affairs
Sponsor
Eng. Mustafa Al-Awa
Project manager
Kinan Azzam

1The proposalAuto-filled

TitleAuto-filled
e-Litigation & Judicial Notification Platform — Release 2
Proposed byAuto-filled
Kinan Azzam
DepartmentAuto-filled
Contracts & Legislation Directorate
Submitted onAuto-filled
⁦2024-10-06⁩
Proposal numberAuto-filled
DMD-2026-008

2Justification

Release 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.

3Objectives

  1. Integrated digital government services for citizens
  2. Sound governance and effective follow-up of projects and data

Strategic objectives served

  • SO-5.1 — Integrated digital government services for citizens
  • SO-5.2 — Sound governance and effective follow-up of projects and data

4Expected benefits

KindBenefit
ProductivityCases filed and served online — target 900 requests

5Cost & feasibility

Estimated cost

SYP 460M

Funding

The delivering body’s investment-plan allocations

Cost lineAmount
Main contractSYP 330M
Supervision & consultingSYP 65M
Internal teamSYP 42.5M
Contingency reserve (5%)SYP 22.5M
TotalSYP 460M

6Initial risks

RiskLevelProposed response
No initial risks recorded

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Kinan AzzamSenior Digital Delivery Consultant — National PMOSubmitted—⁦2024-10-06⁩ 10:13
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2024-10-08⁩ 14:23
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2024-10-09⁩ 09:30
4Portfolio manager reviewTechnical acceptanceBasel Al-MahayniPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-10-13⁩ 10:37
5Cost & funding reviewFinancial approvalApproval engineFinancePre-breach alert—⁦2024-10-16⁩ 08:00
6Cost & funding reviewFinancial approvalRasha Al-MudarresFinanceApproved—⁦2024-10-17⁩ 10:49
7Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2024-10-23⁩ 12:51

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2024-10-08⁩

PMO review

Mariam Al-Zoubi

Approved⁦2024-10-09⁩

Portfolio manager review

Basel Al-Mahayni

Approved⁦2024-10-13⁩

Cost & funding review

Rasha Al-Mudarres

Approved⁦2024-10-17⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2024-10-23⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Kinan Azzam on ⁦2024-10-06⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2024-10-08⁩ at ⁦14:23⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-10-09⁩ at ⁦09:30⁩

  3. Technical acceptance

    Portfolio manager review

    Basel Al-Mahayni · Portfolio manager

    Approved · ⁦2024-10-13⁩ at ⁦10:37⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2024-10-17⁩ at ⁦10:49⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2024-10-23⁩ at ⁦12:51⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-10-27⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Kinan Azzam

  2. V1Returned for edit⁦2024-10-06⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal