Hama National Hospital Upgrade & Extension
Remove from watchlistExtending Hama National Hospital with a new wing of 42 wards and theatres and upgrading its medical equipment, running 9 temporary wards so care never stops during the works.
Budget (BAC)
Actual cost
70% of budget
Progress
Estimate at completion
+SYP 3.5B
SPI · CPI
Forecast finish
152 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure7 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth