PRJ-2026-007Critical4ExecutionConstructionStalledDelivered by:Ministry of Health
Hama National Hospital Upgrade & Extension
Remove from watchlist
Extending Hama National Hospital with a new wing of 42 wards and theatres and upgrading its medical equipment, running 9 temporary wards so care never stops during the works.
Early warning: 97% chance of slipping within 30 days
Budget (BAC)
SYP 16B
Actual cost
SYP 11.1B
70% of budget
Progress
57%Awaiting acceptance 10%
Estimate at completion
SYP 19.5B
+SYP 3.5B
SPI · CPI
0.70Schedule performance index · 0.700.82Cost performance index · 0.82
Forecast finish
2027-06-01
152 days behind baseline
Execution·Stage 4 of 5
Next gate:Closure7 October 2026
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.