Project status card
28 October 2026
Hama National Hospital Upgrade & Extension
PRJ-2026-007 · Development Projects Follow-up Sector · Strategic · WP-2024-007
- Progress
- 57% / 82%
- SPI · CPI
- 0.70 · 0.82
- Spend
- SYP 11.1B / SYP 16B
- Estimate at completion
- SYP 19.5B
Schedule
Planned to date 82%
Forecast finish: 2027-06-01 · 152 days late
SPI0.70Schedule performance index · 0.70CPI0.82Cost performance index · 0.82Health dimensions
Last update: 2026-10-19 · Up to date
Deliverables
4 of 11 due deliverables accepted on time (36%)
Next milestones
- Testing & acceptance complete2027-04-15
- Final handover2027-06-02
Top risks
- Contractor’s financial claims piling up over unapproved change orders20
- Late delivery of operating-theatre equipment from the overseas supplier16
- Possible termination of the MEP subcontractor15
Open impediments
- Finishing works in the new wing stopped — samples not approved · Escalated
- MEP contractor short of skilled labour · Open
- Dispute over the pricing of variation order 7 · Escalated
Decisions and changes waiting
- Hama National Hospital 150-day extension
- Decide on escalated certificate 25 — Hama National Hospital
- Decide on taking the Hama hospital claims to the dispute committee
- CR-2026-005 · Change order 7: medical gases and HVAC redesign
Copilot summary
The scope holds 1 project with a budget of SYP 16bn: 0 on track and 1 red or critical. Weighted progress is 57% against 82% planned, spend SYP 11.12bn, and EAC SYP 19.51bn (SYP 3.51bn over).
1 project is more than a month behind baseline; the worst: Hama National Hospital Upgrade & Extension (152 days).