PSA/2025/006
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
75% of the current value paid
Paid
SYP1.8Bof a current value of SYP 2.4B
Value of each certificate
The last 13 — gross and net
Approved: 12
Count: 13 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | Net | Status | |
|---|---|---|---|---|---|---|---|
| Certificate 13September 2026 | 2026-10-11 | SYP122.5M | SYP12.3M | SYP12.3M | SYP98M | In review | |
| Certificate 12August 2026 | 2026-09-08 | SYP140M | SYP14M | SYP14M | SYP112M | Approved | |
| Certificate 11July 2026 | 2026-08-07 | SYP72M | SYP7.2M | SYP7.2M | SYP57.6M | Approved | |
| Certificate 10June 2026 | 2026-06-27 | SYP125.5M | SYP12.6M | SYP12.6M | SYP100.4M | Approved | |
| Certificate 9April 2026 | 2026-05-16 | SYP146.3M | SYP14.6M | SYP14.6M | SYP117M | Approved | |
| Certificate 8March 2026 | 2026-04-05 | SYP173.8M | SYP17.4M | SYP17.4M | SYP139M | Approved | |
| Certificate 7February 2026 | 2026-02-22 | SYP219.8M | SYP22M | SYP22M | SYP175.8M | Approved | |
| Certificate 6December 2025 | 2026-01-12 | SYP185.3M | SYP18.5M | SYP18.5M | SYP148.2M | Approved | |
| Certificate 5November 2025 | 2025-12-01 | SYP204M | SYP20.4M | SYP20.4M | SYP163.2M | Approved | |
| Certificate 4October 2025 | 2025-10-21 | SYP192.3M | SYP19.2M | SYP19.2M | SYP153.8M | Approved | |
| Certificate 3August 2025 | 2025-09-09 | SYP138M | SYP13.8M | SYP13.8M | SYP110.4M | Approved | |
| Certificate 2July 2025 | 2025-07-30 | SYP123.5M | SYP12.4M | SYP12.4M | SYP98.8M | Approved | |
| Certificate 1May 2025 | 2025-06-18 | SYP74.8M | SYP7.5M | SYP7.5M | SYP59.8M | Approved |