Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 7
- Date
- 2026-02-22
- Reference
- PAY-2025-006-07
Interim payment certificate no. (7)
For the work of February 2026
- Contract number
- PSA/2025/006
- Tender file no.
- 2503530472
- Contract
- Homs backup data centre — civil & MEP fit-out
- Contractor
- Al-Fayhaa General Contracting Co.
- Contractor tax number
- TX-412548
- Project
- Government Backup Data Centre, Homs — Phase 2
- Contract period
- 2025-05-04 — 2026-11-30
- Original contract value
- SYP2,300,000,000
- Current contract value
- SYP2,377,500,000including variations of SYP 77.5M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 1,137,500,000 |
| 2 | Less: previous certificates | (917,750,000) |
| 3 | Value of work in this certificate | 219,750,000 |
| 4 | Less: retention (10%) | (21,975,000) |
| 5 | Less: advance payment recovery (10%) | (21,975,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (43,950,000) |
| 8 | Net amount payable to the contractor | SYP175,800,000 |
Amount in words: One hundred seventy-five million eight hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 113.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 166,425,000 | 139,775,000 | 26,650,000 | 166,425,000 | 100% |
| Earthworks & foundations | 427,950,000 | 252,625,000 | 51,300,000 | 303,925,000 | 71% |
| Concrete & structural works | 737,025,000 | 312,325,000 | 75,575,000 | 387,900,000 | 53% |
| Mechanical, electrical & plumbing | 570,600,000 | 147,250,000 | 43,850,000 | 191,100,000 | 33% |
| Finishes & external works | 356,625,000 | 57,475,000 | 19,300,000 | 76,775,000 | 22% |
| Testing & commissioning | 118,875,000 | 8,300,000 | 3,075,000 | 11,375,000 | 10% |
| Total | 2,377,500,000 | 917,750,000 | 219,750,000 | 1,137,500,000 | 48% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Walid Al-Masri
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. George Haddad
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar