Certificate ⁦7⁩ — February 2026

Homs backup data centre — civil & MEP fit-out

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
7
Date
⁦2026-02-22⁩
Reference
PAY-2025-006-07

Interim payment certificate no. (⁦7⁩)

For the work of February 2026

Contract number
PSA/2025/006
Tender file no.
2503530472
Contract
Homs backup data centre — civil & MEP fit-out
Contractor
Al-Fayhaa General Contracting Co.
Contractor tax number
TX-412548
Project
Government Backup Data Centre, Homs — Phase 2
Contract period
⁦2025-05-04⁩ — ⁦2026-11-30⁩
Original contract value
SYP2,300,000,000
Current contract value
SYP2,377,500,000including variations of SYP 77.5M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date1,137,500,000
2Less: previous certificates(917,750,000)
3Value of work in this certificate219,750,000
4Less: retention (⁦10%⁩)(21,975,000)
5Less: advance payment recovery (⁦10%⁩)(21,975,000)
6Less: delay and breach penalties0
7Total deductions(43,950,000)
8Net amount payable to the contractorSYP175,800,000

Amount in words: One hundred seventy-five million eight hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 113.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation166,425,000139,775,00026,650,000166,425,000⁦100%⁩
Earthworks & foundations427,950,000252,625,00051,300,000303,925,000⁦71%⁩
Concrete & structural works737,025,000312,325,00075,575,000387,900,000⁦53%⁩
Mechanical, electrical & plumbing570,600,000147,250,00043,850,000191,100,000⁦33%⁩
Finishes & external works356,625,00057,475,00019,300,00076,775,000⁦22%⁩
Testing & commissioning118,875,0008,300,0003,075,00011,375,000⁦10%⁩
Total2,377,500,000917,750,000219,750,0001,137,500,000⁦48%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Walid Al-Masri

Al-Masri⁦2026-02-22⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-02-24⁩

Project manager

Eng. George Haddad

Haddad⁦2026-02-27⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-03-02⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-03-05⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-02-22⁩

    Eng. Walid Al-Masri

  2. Engineer verifies quantities⁦2026-02-24⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-02-27⁩

    Eng. George Haddad · Director, Data Centres & Government Network

    Took 3 days

  4. Payment order prepared⁦2026-03-02⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-03-05⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-03-16⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-10-26⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. George Haddad → Dr. Samer Al-Daqqar

Certificate history

5 March 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-03-05 13:00

2 March 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-03-02 13:00

27 February 2026

  1. Approval: Eng. George Haddad signed “Project manager certifies”

    2026-02-27 13:00

24 February 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-02-24 13:00

22 February 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-02-22 09:00