Certificate ⁦10⁩ — June 2026

Homs backup data centre — civil & MEP fit-out

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
10
Date
⁦2026-06-27⁩
Reference
PAY-2025-006-10

Interim payment certificate no. (⁦10⁩)

For the work of June 2026

Contract number
PSA/2025/006
Tender file no.
2503530472
Contract
Homs backup data centre — civil & MEP fit-out
Contractor
Al-Fayhaa General Contracting Co.
Contractor tax number
TX-412548
Project
Government Backup Data Centre, Homs — Phase 2
Contract period
⁦2025-05-04⁩ — ⁦2026-11-30⁩
Original contract value
SYP2,300,000,000
Current contract value
SYP2,377,500,000including variations of SYP 77.5M
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date1,583,000,000
2Less: previous certificates(1,457,500,000)
3Value of work in this certificate125,500,000
4Less: retention (⁦10%⁩)(12,550,000)
5Less: advance payment recovery (⁦10%⁩)(12,550,000)
6Less: delay and breach penalties0
7Total deductions(25,100,000)
8Net amount payable to the contractorSYP100,400,000

Amount in words: One hundred million four hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 158.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation166,425,000157,250,0009,175,000166,425,000⁦100%⁩
Earthworks & foundations427,950,000401,775,00026,175,000427,950,000⁦100%⁩
Concrete & structural works737,025,000552,325,00047,675,000600,000,000⁦81%⁩
Mechanical, electrical & plumbing570,600,000238,325,00027,625,000265,950,000⁦47%⁩
Finishes & external works356,625,00094,125,00012,725,000106,850,000⁦30%⁩
Testing & commissioning118,875,00013,700,0002,125,00015,825,000⁦13%⁩
Total2,377,500,0001,457,500,000125,500,0001,583,000,000⁦67%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Walid Al-Masri

Al-Masri⁦2026-06-27⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-06-29⁩

Project manager

Eng. George Haddad

Haddad⁦2026-07-02⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-07-05⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-07-08⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-06-27⁩

    Eng. Walid Al-Masri

  2. Engineer verifies quantities⁦2026-06-29⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-07-02⁩

    Eng. George Haddad · Director, Data Centres & Government Network

    Took 3 days

  4. Payment order prepared⁦2026-07-05⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-07-08⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-07-27⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. George Haddad → Dr. Samer Al-Daqqar

Certificate history

8 July 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-07-08 13:00

5 July 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-07-05 13:00

2 July 2026

  1. Approval: Eng. George Haddad signed “Project manager certifies”

    2026-07-02 13:00

29 June 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-06-29 13:00

27 June 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-06-27 09:00