Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 11
- Date
- 2026-08-07
- Reference
- PAY-2025-006-11
Interim payment certificate no. (11)
For the work of July 2026
- Contract number
- PSA/2025/006
- Tender file no.
- 2503530472
- Contract
- Homs backup data centre — civil & MEP fit-out
- Contractor
- Al-Fayhaa General Contracting Co.
- Contractor tax number
- TX-412548
- Project
- Government Backup Data Centre, Homs — Phase 2
- Contract period
- 2025-05-04 — 2026-11-30
- Original contract value
- SYP2,300,000,000
- Current contract value
- SYP2,377,500,000including variations of SYP 77.5M
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 1,655,000,000 |
| 2 | Less: previous certificates | (1,583,000,000) |
| 3 | Value of work in this certificate | 72,000,000 |
| 4 | Less: retention (10%) | (7,200,000) |
| 5 | Less: advance payment recovery (10%) | (7,200,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (14,400,000) |
| 8 | Net amount payable to the contractor | SYP57,600,000 |
Amount in words: Fifty-seven million six hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 165.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 166,425,000 | 161,600,000 | 4,825,000 | 166,425,000 | 100% |
| Earthworks & foundations | 427,950,000 | 414,025,000 | 13,925,000 | 427,950,000 | 100% |
| Concrete & structural works | 737,025,000 | 625,900,000 | 28,400,000 | 654,300,000 | 89% |
| Mechanical, electrical & plumbing | 570,600,000 | 261,950,000 | 16,100,000 | 278,050,000 | 49% |
| Finishes & external works | 356,625,000 | 104,250,000 | 7,475,000 | 111,725,000 | 31% |
| Testing & commissioning | 118,875,000 | 15,275,000 | 1,275,000 | 16,550,000 | 14% |
| Total | 2,377,500,000 | 1,583,000,000 | 72,000,000 | 1,655,000,000 | 70% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Walid Al-Masri
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. George Haddad
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar