Certificate ⁦6⁩ — December 2025

Homs backup data centre — civil & MEP fit-out

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
6
Date
⁦2026-01-12⁩
Reference
PAY-2025-006-06

Interim payment certificate no. (⁦6⁩)

For the work of December 2025

Contract number
PSA/2025/006
Tender file no.
2503530472
Contract
Homs backup data centre — civil & MEP fit-out
Contractor
Al-Fayhaa General Contracting Co.
Contractor tax number
TX-412548
Project
Government Backup Data Centre, Homs — Phase 2
Contract period
⁦2025-05-04⁩ — ⁦2026-11-30⁩
Original contract value
SYP2,300,000,000
Current contract value
SYP2,377,500,000including variations of SYP 77.5M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date917,750,000
2Less: previous certificates(732,500,000)
3Value of work in this certificate185,250,000
4Less: retention (⁦10%⁩)(18,525,000)
5Less: advance payment recovery (⁦10%⁩)(18,525,000)
6Less: delay and breach penalties0
7Total deductions(37,050,000)
8Net amount payable to the contractorSYP148,200,000

Amount in words: One hundred forty-eight million two hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 91.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation166,425,000122,075,00026,150,000148,225,000⁦89%⁩
Earthworks & foundations427,950,000188,900,00042,375,000231,275,000⁦54%⁩
Concrete & structural works737,025,000249,350,00063,600,000312,950,000⁦42%⁩
Mechanical, electrical & plumbing570,600,000118,725,00035,450,000154,175,000⁦27%⁩
Finishes & external works356,625,00046,675,00015,275,00061,950,000⁦17%⁩
Testing & commissioning118,875,0006,775,0002,400,0009,175,000⁦8%⁩
Total2,377,500,000732,500,000185,250,000917,750,000⁦39%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Walid Al-Masri

Al-Masri⁦2026-01-12⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-01-14⁩

Project manager

Eng. George Haddad

Haddad⁦2026-01-17⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-01-20⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-01-23⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-01-12⁩

    Eng. Walid Al-Masri

  2. Engineer verifies quantities⁦2026-01-14⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-01-17⁩

    Eng. George Haddad · Director, Data Centres & Government Network

    Took 3 days

  4. Payment order prepared⁦2026-01-20⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-01-23⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-03-16⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-10-26⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. George Haddad → Dr. Samer Al-Daqqar

Certificate history

23 January 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-01-23 13:00

20 January 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-01-20 13:00

17 January 2026

  1. Approval: Eng. George Haddad signed “Project manager certifies”

    2026-01-17 13:00

14 January 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-01-14 13:00

12 January 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-01-12 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close