Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 6
- Date
- 2026-01-12
- Reference
- PAY-2025-006-06
Interim payment certificate no. (6)
For the work of December 2025
- Contract number
- PSA/2025/006
- Tender file no.
- 2503530472
- Contract
- Homs backup data centre — civil & MEP fit-out
- Contractor
- Al-Fayhaa General Contracting Co.
- Contractor tax number
- TX-412548
- Project
- Government Backup Data Centre, Homs — Phase 2
- Contract period
- 2025-05-04 — 2026-11-30
- Original contract value
- SYP2,300,000,000
- Current contract value
- SYP2,377,500,000including variations of SYP 77.5M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 917,750,000 |
| 2 | Less: previous certificates | (732,500,000) |
| 3 | Value of work in this certificate | 185,250,000 |
| 4 | Less: retention (10%) | (18,525,000) |
| 5 | Less: advance payment recovery (10%) | (18,525,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (37,050,000) |
| 8 | Net amount payable to the contractor | SYP148,200,000 |
Amount in words: One hundred forty-eight million two hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 91.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 166,425,000 | 122,075,000 | 26,150,000 | 148,225,000 | 89% |
| Earthworks & foundations | 427,950,000 | 188,900,000 | 42,375,000 | 231,275,000 | 54% |
| Concrete & structural works | 737,025,000 | 249,350,000 | 63,600,000 | 312,950,000 | 42% |
| Mechanical, electrical & plumbing | 570,600,000 | 118,725,000 | 35,450,000 | 154,175,000 | 27% |
| Finishes & external works | 356,625,000 | 46,675,000 | 15,275,000 | 61,950,000 | 17% |
| Testing & commissioning | 118,875,000 | 6,775,000 | 2,400,000 | 9,175,000 | 8% |
| Total | 2,377,500,000 | 732,500,000 | 185,250,000 | 917,750,000 | 39% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Walid Al-Masri
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. George Haddad
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar