Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 5
- Date
- 2025-12-01
- Reference
- PAY-2025-006-05
Interim payment certificate no. (5)
For the work of November 2025
- Contract number
- PSA/2025/006
- Tender file no.
- 2503530472
- Contract
- Homs backup data centre — civil & MEP fit-out
- Contractor
- Al-Fayhaa General Contracting Co.
- Contractor tax number
- TX-412548
- Project
- Government Backup Data Centre, Homs — Phase 2
- Contract period
- 2025-05-04 — 2026-11-30
- Original contract value
- SYP2,300,000,000
- Current contract value
- SYP2,377,500,000including variations of SYP 77.5M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 732,500,000 |
| 2 | Less: previous certificates | (528,500,000) |
| 3 | Value of work in this certificate | 204,000,000 |
| 4 | Less: retention (10%) | (20,400,000) |
| 5 | Less: advance payment recovery (10%) | (20,400,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (40,800,000) |
| 8 | Net amount payable to the contractor | SYP163,200,000 |
Amount in words: One hundred sixty-three million two hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 73.3M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 166,425,000 | 88,425,000 | 29,875,000 | 118,300,000 | 71% |
| Earthworks & foundations | 427,950,000 | 136,725,000 | 47,875,000 | 184,600,000 | 43% |
| Concrete & structural works | 737,025,000 | 179,875,000 | 69,900,000 | 249,775,000 | 34% |
| Mechanical, electrical & plumbing | 570,600,000 | 85,250,000 | 37,800,000 | 123,050,000 | 22% |
| Finishes & external works | 356,625,000 | 33,400,000 | 16,050,000 | 49,450,000 | 14% |
| Testing & commissioning | 118,875,000 | 4,825,000 | 2,500,000 | 7,325,000 | 6% |
| Total | 2,377,500,000 | 528,500,000 | 204,000,000 | 732,500,000 | 31% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Walid Al-Masri
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. George Haddad
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar