Certificate ⁦2⁩ — July 2025

Homs backup data centre — civil & MEP fit-out

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
2
Date
⁦2025-07-30⁩
Reference
PAY-2025-006-02

Interim payment certificate no. (⁦2⁩)

For the work of July 2025

Contract number
PSA/2025/006
Tender file no.
2503530472
Contract
Homs backup data centre — civil & MEP fit-out
Contractor
Al-Fayhaa General Contracting Co.
Contractor tax number
TX-412548
Project
Government Backup Data Centre, Homs — Phase 2
Contract period
⁦2025-05-04⁩ — ⁦2026-11-30⁩
Original contract value
SYP2,300,000,000
Current contract value
SYP2,377,500,000including variations of SYP 77.5M
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SYP)

1Total value of work completed to date198,250,000
2Less: previous certificates(74,750,000)
3Value of work in this certificate123,500,000
4Less: retention (⁦10%⁩)(12,350,000)
5Less: advance payment recovery (⁦10%⁩)(12,350,000)
6Less: delay and breach penalties0
7Total deductions(24,700,000)
8Net amount payable to the contractorSYP98,800,000

Amount in words: Ninety-eight million eight hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 19.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation166,425,00012,500,00019,550,00032,050,000⁦19%⁩
Earthworks & foundations427,950,00019,325,00030,625,00049,950,000⁦12%⁩
Concrete & structural works737,025,00025,450,00042,150,00067,600,000⁦9%⁩
Mechanical, electrical & plumbing570,600,00012,075,00021,225,00033,300,000⁦6%⁩
Finishes & external works356,625,0004,725,0008,650,00013,375,000⁦4%⁩
Testing & commissioning118,875,000675,0001,300,0001,975,000⁦2%⁩
Total2,377,500,00074,750,000123,500,000198,250,000⁦8%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Walid Al-Masri

Al-Masri⁦2025-07-30⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-08-01⁩

Project manager

Eng. George Haddad

Haddad⁦2025-08-04⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-08-07⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-08-10⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-07-30⁩

    Eng. Walid Al-Masri

  2. Engineer verifies quantities⁦2025-08-01⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-08-04⁩

    Eng. George Haddad · Director, Data Centres & Government Network

    Took 3 days

  4. Payment order prepared⁦2025-08-07⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-08-10⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-10-12⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-03-17⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. George Haddad → Dr. Samer Al-Daqqar

Certificate history

10 August 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-08-10 13:00

7 August 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-08-07 13:00

4 August 2025

  1. Approval: Eng. George Haddad signed “Project manager certifies”

    2025-08-04 13:00

1 August 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-08-01 13:00

30 July 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-07-30 09:00