PSA/2024/012
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
100% of the current value paid
Paid
SYP220Mof a current value of SYP 220M
Value of each certificate
The last 11 — gross and net
Approved: 11
Count: 11 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | Net | Status | |
|---|---|---|---|---|---|---|---|
| Certificate 11October 2025 | 2025-10-25 | SYP9.5M | SYP475K | SYP950K | SYP8.1M | Approved | |
| Certificate 10August 2025 | 2025-09-09 | SYP16.8M | SYP837.5K | SYP1.7M | SYP14.2M | Approved | |
| Certificate 9July 2025 | 2025-07-24 | SYP19.5M | SYP975K | SYP2M | SYP16.6M | Approved | |
| Certificate 8May 2025 | 2025-06-08 | SYP23M | SYP1.2M | SYP2.3M | SYP19.6M | Approved | |
| Certificate 7April 2025 | 2025-04-22 | SYP29.3M | SYP1.5M | SYP2.9M | SYP24.9M | Approved | |
| Certificate 6February 2025 | 2025-03-07 | SYP24.8M | SYP1.2M | SYP2.5M | SYP21M | Approved | |
| Certificate 5December 2024 | 2025-01-19 | SYP27M | SYP1.4M | SYP2.7M | SYP23M | Approved | |
| Certificate 4November 2024 | 2024-12-04 | SYP25.5M | SYP1.3M | SYP2.6M | SYP21.7M | Approved | |
| Certificate 3September 2024 | 2024-10-18 | SYP18.3M | SYP912.5K | SYP1.8M | SYP15.5M | Approved | |
| Certificate 2August 2024 | 2024-09-02 | SYP16.5M | SYP825K | SYP1.7M | SYP14M | Approved | |
| Certificate 1June 2024 | 2024-07-17 | SYP10M | SYP500K | SYP1M | SYP8.5M | Approved |