Certificate ⁦11⁩ — October 2025

Government HR self-service implementation

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
11
Date
⁦2025-10-25⁩
Reference
PAY-2024-012-11

Interim payment certificate no. (⁦11⁩)

For the work of October 2025

Contract number
PSA/2024/012
Tender file no.
2401850160
Contract
Government HR self-service implementation
Contractor
Integrated Financial & Administrative Systems Co.
Contractor tax number
TX-440781
Project
Government HR System — Employee Self-Service
Contract period
⁦2024-06-02⁩ — ⁦2025-09-30⁩
Original contract value
SYP220,000,000
Current contract value
SYP220,000,000
Linked milestone
Hypercare & handover · MS-G5 Final handover

Certificate summary (SYP)

1Total value of work completed to date220,000,000
2Less: previous certificates(210,500,000)
3Value of work in this certificate9,500,000
4Less: retention (⁦5%⁩)(475,000)
5Less: advance payment recovery (⁦10%⁩)(950,000)
6Less: delay and breach penalties0
7Total deductions(1,425,000)
8Net amount payable to the contractorSYP8,075,000

Amount in words: Eight million seventy-five thousand Syrian pounds only

Retention held up to this certificate: SYP 11M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Analysis & design33,000,00032,525,000475,00033,000,000⁦100%⁩
Licences & platform44,000,00043,075,000925,00044,000,000⁦100%⁩
Build & configuration66,000,00063,200,0002,800,00066,000,000⁦100%⁩
Systems integration33,000,00031,125,0001,875,00033,000,000⁦100%⁩
Testing & acceptance22,000,00020,450,0001,550,00022,000,000⁦100%⁩
Training & run22,000,00020,125,0001,875,00022,000,000⁦100%⁩
Total220,000,000210,500,0009,500,000220,000,000⁦100%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Mona Khaddour

Khaddour⁦2025-10-25⁩

Supervising engineer

Hamza Al-Hussein

Al-Hussein⁦2025-10-27⁩

Project manager

Nour Al-Jabiri

Al-Jabiri⁦2025-10-30⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-11-02⁩

Final approver

Rasha Al-Mudarres

Al-Mudarres⁦2025-11-05⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-10-25⁩

    Mona Khaddour

  2. Engineer verifies quantities⁦2025-10-27⁩

    Hamza Al-Hussein · Senior Software Engineer – Integration

    Took 2 days

  3. Project manager certifies⁦2025-10-30⁩

    Nour Al-Jabiri · Director, Government Systems & Integration

    Took 3 days

  4. Payment order prepared⁦2025-11-02⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-11-05⁩

    Rasha Al-Mudarres · Director General, Finance & Contracts

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneHypercare & handoverDone · ⁦2025-09-30⁩
  2. Project milestoneMS-G5Final handoverMilestone approved ⁦2025-09-21⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Rasha Al-Mudarres
  • Whoever verified quantities does not prepare the payment orderHamza Al-Hussein → Omar Al-Nahhas
  • The project manager does not approve the paymentNour Al-Jabiri → Rasha Al-Mudarres

Certificate history

5 November 2025

  1. Payment: Rasha Al-Mudarres signed “Final approval”

    2025-11-05 13:00

2 November 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-11-02 13:00

30 October 2025

  1. Approval: Nour Al-Jabiri signed “Project manager certifies”

    2025-10-30 13:00

27 October 2025

  1. Approval: Hamza Al-Hussein signed “Engineer verifies quantities”

    2025-10-27 13:00

25 October 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-10-25 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close