Planning
Kick-off meeting minutes
Roles, tasks, decisions and the start of execution
- Form no.
- PSA-PMO-F06
- Template edition
- 1.2
- Version
- V1
- Form date
- 2024-10-13
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-036
- Project
- Madinat al-Salam Drinking-Water Network (Quneitra)
- Portfolio
- Energy & Water Portfolio
- Sector
- Development Projects Follow-up Sector
- Sponsor
- Salma Al-Zaim
- Project manager
- Eng. Maher Al-Hamawi
1The meetingAuto-filled
- MeetingAuto-filled
- Kick-off — Madinat al-Salam Drinking-Water Network (Quneitra)
- Date and timeAuto-filled
- 2024-10-13 · 10:00
- PlaceAuto-filled
- Main meeting room — Authority HQ, Kafr Sousa
- SecretaryAuto-filled
- Eng. Maher Al-Hamawi
Purpose
Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.
| Attendees | Title |
|---|---|
| Salma Al-Zaim | Deputy President, Finance, Administration & the Investment Plan |
| Eng. Wassim Al-Azm | Director General, Infrastructure & Reconstruction Projects |
| Eng. Maher Al-Hamawi | Director, Energy, Water & Utilities Projects |
| Dr. Reem Al-Qabbani | Director, National Project Management Office |
2Roles
| Person | Role | Duty |
|---|---|---|
| Salma Al-Zaim | Project sponsor | Sponsors the project, decides escalations and material changes |
| Eng. Wassim Al-Azm | Project owner | Approves the requirements and accepts the deliverables |
| Eng. Maher Al-Hamawi | Project manager | Runs the plan, deliverables and risks; files the periodic update card |
| Dr. Reem Al-Qabbani | Project Management Office | Follows the methodology and checks the periodic updates |
3Tasks
| Task | Owner | Due | Status |
|---|---|---|---|
| Project plan approved | Eng. Maher Al-Hamawi | 2025-03-11 | Done |
| Designs approved | Eng. Maher Al-Hamawi | 2025-07-09 | Done |
| Build complete | Eng. Maher Al-Hamawi | 2026-01-04 | Done |
| Testing & acceptance complete | Eng. Maher Al-Hamawi | 2026-07-03 | Done |
4Decisions
- The charter is the reference for scope, budget and the milestone plan
- Change Committee: Approves scope, cost and schedule changes (Weekly)
- Project Approval Committee: Methodology compliance, data quality, stage gates (Fortnightly)
- The periodic update card monthly, before the 5th of the month
5Start of execution
- Execution starts on
- 2025-02-04
- Start confirmed
- Salma Al-Zaim · 2024-10-14
Approval logChain: Kick-off minutes approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Maher Al-HamawiDirector, Energy, Water & Utilities Projects | Submitted | — | 2024-10-14 14:47 |
| 2 | Chair’s approval (sponsor) | Technical acceptance | Salma Al-ZaimProject sponsor | Approved | — | 2024-10-15 12:30 |
| 3 | Minutes against the template | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | — | 2024-10-16 12:21 |
Signatures
Minutes against the template
Mariam Al-Zoubi
Approved2024-10-16
Chair’s approval (sponsor)
Salma Al-Zaim
Approved2024-10-15