PRJ-2026-036On track5ClosureConstructionIn progressDelivered by:Ministry of Energy

Madinat al-Salam Drinking-Water Network (Quneitra)

Add to watchlist

Rehabilitating the wells, pumping station, main reservoir and distribution network of Madinat al-Salam — closing, with 97% of the works done.

Budget (BAC)

SYP 1.7B

Actual cost

SYP 1.6B

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SYP 1.7B

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-03-10⁩
ApprovedDMD-2026-036Madinat al-Salam Drinking-Water Network (Quneitra)

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-036
Project
Madinat al-Salam Drinking-Water Network (Quneitra)
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Maher Al-Hamawi

1The proposalAuto-filled

TitleAuto-filled
Madinat al-Salam Drinking-Water Network (Quneitra)
Proposed byAuto-filled
Eng. Maher Al-Hamawi
DepartmentAuto-filled
Energy, Water & Utilities Projects Directorate
Submitted onAuto-filled
⁦2024-03-10⁩
Proposal numberAuto-filled
DMD-2026-036

2Justification

Rehabilitating the wells, pumping station, main reservoir and distribution network of Madinat al-Salam — closing, with 97% of the works done.

3Objectives

  1. Rehabilitate core energy, water and transport infrastructure
  2. Comparable public-service quality in every governorate

Strategic objectives served

  • SO-2.1 — Rehabilitate core energy, water and transport infrastructure
  • SO-6.1 — Comparable public-service quality in every governorate

4Expected benefits

KindBenefit
ProductivityResidents served by the rehabilitated Madinat al-Salam network — target 4800 visitors / year

5Cost & feasibility

Estimated cost

SYP 1.7B

Funding

The delivering body’s investment-plan allocations

Cost lineAmount
Main contractSYP 1.2B
Supervision & consultingSYP 235M
Internal teamSYP 150M
Contingency reserve (5%)SYP 85M
TotalSYP 1.7B

6Initial risks

RiskLevelProposed response
Provisional-acceptance remarks on the pumping station and control panelsLowTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsSubmitted—⁦2024-03-10⁩ 11:50
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2024-03-11⁩ 09:30
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2024-03-13⁩ 10:37
4Portfolio manager reviewTechnical acceptanceEng. Rami YoussefPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-03-18⁩ 11:44
5Cost & funding reviewFinancial approvalRasha Al-MudarresFinanceApproved—⁦2024-03-21⁩ 11:26
6Project Approval CommitteeTechnical acceptanceApproval engineProject Approval CommitteePre-breach alert—⁦2024-03-27⁩ 08:00
7Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2024-03-28⁩ 13:58

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2024-03-11⁩

PMO review

Mariam Al-Zoubi

Approved⁦2024-03-13⁩

Portfolio manager review

Eng. Rami Youssef

Approved⁦2024-03-18⁩

Cost & funding review

Rasha Al-Mudarres

Approved⁦2024-03-21⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2024-03-28⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Maher Al-Hamawi on ⁦2024-03-10⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2024-03-11⁩ at ⁦09:30⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-03-13⁩ at ⁦10:37⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Rami Youssef · Portfolio manager

    Approved · ⁦2024-03-18⁩ at ⁦11:44⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2024-03-21⁩ at ⁦11:26⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2024-03-28⁩ at ⁦13:58⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-03-31⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Maher Al-Hamawi

  2. V1Returned for edit⁦2024-03-10⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Maher Al-Hamawi

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close