PRJ-2026-033On hold3PlanningConstructionStoppedDelivered by:Ministry of Health

Al-Mayadin General Hospital

Add to watchlist

A general hospital in Al-Mayadin serving the eastern Deir ez-Zor countryside with emergency, surgery, paediatrics and maternity — paused until the governorate council completes the land allocation.

Budget (BAC)

SYP 5.3B

Actual cost

SYP 105M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 5.3B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

0Achieved
0On track
4At risk
1Late
Average delay182 days
Oct 26Jan 27Apr 27Jul 27Oct 27Jan 28Apr 28Jul 28Oct 28Jan 29
Contractual
Build completePlanned: ⁦2027-07-28⁩Forecast / actual: ⁦2028-01-26⁩Delay: 182 daysG3 +182
Executive
Project plan approvedPlanned: ⁦2026-08-24⁩Forecast / actual: ⁦2027-02-15⁩Delay: 175 daysG1 +175
Payment
Final handoverPlanned: ⁦2028-06-30⁩Forecast / actual: ⁦2029-01-05⁩Delay: 189 daysG5 +189
Regulatory
Testing & acceptance completePlanned: ⁦2028-02-16⁩Forecast / actual: ⁦2028-08-20⁩Delay: 186 daysG4 +186
Project
Designs approvedPlanned: ⁦2027-01-06⁩Forecast / actual: ⁦2027-07-03⁩Delay: 178 daysG2 +178

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-08-24⁩⁦2027-02-15⁩⁦+175⁩ daysEng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.syLate0Not requested
Designs approvedMS-G2Project⁦2027-01-06⁩⁦2027-07-03⁩⁦+178⁩ daysEng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.syAt risk0Not requested
Build completeMS-G3Contractual⁦2027-07-28⁩⁦2028-01-26⁩⁦+182⁩ daysEng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.syAt risk0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2028-02-16⁩⁦2028-08-20⁩⁦+186⁩ daysEng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.syAt risk0Not requested
Final handoverMS-G5Payment⁦2028-06-30⁩⁦2029-01-05⁩⁦+189⁩ daysEng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.syAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦2%⁩

Awaiting acceptance

⁦0%⁩

Not handed in

⁦98%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline033-D1⁦2%⁩CRT-033-01ApprovedEng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.syEng. Wassim Al-Azm⁦2026-06-17⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting033-D2⁦3%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-08-24⁩V0⁦0⁩ of ⁦3⁩
Detailed design033-D3⁦6%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-10-30⁩V0⁦0⁩ of ⁦3⁩
Permits & approvals033-D4⁦6%⁩—DraftEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syEng. Wassim Al-Azm⁦2027-01-06⁩V0⁦0⁩ of ⁦3⁩
Site works & excavation033-D5⁦13%⁩—DraftEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syEng. Wassim Al-Azm⁦2027-03-15⁩V0⁦0⁩ of ⁦3⁩
Structure033-D6⁦13%⁩—DraftEng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.syEng. Wassim Al-Azm⁦2027-05-21⁩V0⁦0⁩ of ⁦3⁩
Finishes033-D7⁦13%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2027-07-28⁩V0⁦0⁩ of ⁦3⁩
Supply033-D8⁦10%⁩—DraftEng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.syEng. Wassim Al-Azm⁦2027-10-04⁩V0⁦0⁩ of ⁦3⁩
Installation033-D9⁦10%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2027-12-10⁩V0⁦0⁩ of ⁦3⁩
Testing & commissioning033-D10⁦10%⁩—DraftEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syEng. Wassim Al-Azm⁦2028-02-16⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance033-D11⁦7%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2028-04-23⁩V0⁦0⁩ of ⁦3⁩
Final acceptance033-D12⁦7%⁩—DraftEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syEng. Wassim Al-Azm⁦2028-06-30⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩
⁦1⁩–⁦12⁩ of ⁦12⁩