PRJ-2026-033On hold3PlanningConstructionStoppedDelivered by:Ministry of Health

Al-Mayadin General Hospital

Add to watchlist

A general hospital in Al-Mayadin serving the eastern Deir ez-Zor countryside with emergency, surgery, paediatrics and maternity — paused until the governorate council completes the land allocation.

Budget (BAC)

SYP 5.3B

Actual cost

SYP 105M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 5.3B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-08-03⁩
ApprovedDMD-2026-033Al-Mayadin General Hospital

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-033
Project
Al-Mayadin General Hospital
Portfolio
Health, Education & Industrial Recovery Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Eng. Bashir Al-Tai
Project manager
Eng. Sara Al-Barazi

1The proposalAuto-filled

TitleAuto-filled
Al-Mayadin General Hospital
Proposed byAuto-filled
Eng. Sara Al-Barazi
DepartmentAuto-filled
Health Projects Directorate
Submitted onAuto-filled
⁦2025-08-03⁩
Proposal numberAuto-filled
DMD-2026-033

2Justification

A general hospital in Al-Mayadin serving the eastern Deir ez-Zor countryside with emergency, surgery, paediatrics and maternity — paused until the governorate council completes the land allocation.

3Objectives

  1. Better access to health and education
  2. Comparable public-service quality in every governorate

Strategic objectives served

  • SO-3.1 — Better access to health and education
  • SO-6.1 — Comparable public-service quality in every governorate

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SYP 5.3B

Funding

The delivering body’s investment-plan allocations

Cost lineAmount
Main contractSYP 3.8B
Supervision & consultingSYP 735M
Internal teamSYP 472.5M
Contingency reserve (5%)SYP 262.5M
TotalSYP 5.3B

6Initial risks

RiskLevelProposed response
Late land allocation and registration by the Deir ez-Zor governorate councilHighTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesSubmitted—⁦2025-08-03⁩ 14:29
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2025-08-05⁩ 12:39
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-08-07⁩ 13:46
4Portfolio manager reviewTechnical acceptanceEng. Fadi Al-DroubiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-08-12⁩ 14:53
5Cost & funding reviewFinancial approvalApproval engineFinancePre-breach alert—⁦2025-08-17⁩ 08:00
6Cost & funding reviewFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-08-18⁩ 14:05
7Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2025-08-20⁩ 10:07

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2025-08-05⁩

PMO review

Mariam Al-Zoubi

Approved⁦2025-08-07⁩

Portfolio manager review

Eng. Fadi Al-Droubi

Approved⁦2025-08-12⁩

Cost & funding review

Rasha Al-Mudarres

Approved⁦2025-08-18⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2025-08-20⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Sara Al-Barazi on ⁦2025-08-03⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2025-08-05⁩ at ⁦12:39⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-08-07⁩ at ⁦13:46⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Fadi Al-Droubi · Portfolio manager

    Approved · ⁦2025-08-12⁩ at ⁦14:53⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-08-18⁩ at ⁦14:05⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2025-08-20⁩ at ⁦10:07⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-08-24⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Sara Al-Barazi

  2. V1Returned for edit⁦2025-08-03⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Sara Al-Barazi