Latakia University Technical Engineering Faculty Extension Subtask Last item under this branch 2027-03-11 52% Latakia University Technical Engineering Faculty Extension Planned: 2025-03-16 → 2027-02-28 Forecast: 2025-03-16 → 2027-03-11 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-11-04 100% Management & governance Planned: 2025-03-16 → 2025-08-10 Actual: 2025-03-16 → 2025-11-04
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-08-06 100% Project plan & baseline Planned: 2025-03-16 → 2025-06-15 Actual: 2025-03-16 → 2025-08-06
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-11-04 100% Monitoring & reporting Planned: 2025-05-12 → 2025-08-10 Actual: 2025-06-14 → 2025-11-04
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-11-04 100% Project plan approved Planned: 2025-08-10 → 2025-08-10 Actual: 2025-11-04 → 2025-11-04 Project plan approved
2 Design & permits Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-05-02 100% Design & permits Planned: 2025-07-07 → 2025-12-02 Actual: 2025-09-11 → 2026-05-02
2.1 Detailed design Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-02-01 100% Detailed design Planned: 2025-07-07 → 2025-10-06 Actual: 2025-09-11 → 2026-02-01
2.2 Permits & approvals Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-02 100% Permits & approvals Planned: 2025-09-02 → 2025-12-02 Actual: 2025-12-10 → 2026-05-02
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-02 100% Designs approved Planned: 2025-12-02 → 2025-12-02 Actual: 2026-05-02 → 2026-05-02 Designs approved
3 Civil works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-11-26 89% Civil works Planned: 2025-10-29 → 2026-05-21 Forecast: 2026-02-19 → 2026-11-26 Float: 0d
3.1 Site works & excavation Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-30 100% Site works & excavation Planned: 2025-10-29 → 2026-01-27 Actual: 2026-03-09 → 2026-07-30
3.2 Structure Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Structure Planned: 2025-12-24 → 2026-03-25 Actual: 2026-06-07 → 2026-10-26
3.3 Finishes Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-26 68% Finishes Planned: 2026-02-19 → 2026-05-21 Forecast: 2026-02-19 → 2026-11-26 Float: 0d Drag to change its duration +189
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-26 0% Build complete Planned: 2026-05-21 → 2026-05-21 Forecast: 2026-11-26 → 2026-11-26 Float: 105d Drag to change its dates Build complete
4 MEP works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-28 0% MEP works Planned: 2026-04-17 → 2026-11-07 Forecast: 2026-11-13 → 2027-01-28 Float: 0d
4.1 Supply Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-17 0% Supply Planned: 2026-04-17 → 2026-07-16 Forecast: 2026-11-13 → 2026-12-17 Float: 0d Drag to change its dates +154
4.2 Installation Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-07 0% Installation Planned: 2026-06-12 → 2026-09-11 Forecast: 2026-12-04 → 2027-01-07 Float: 0d Drag to change its dates +118
4.3 Testing & commissioning Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-28 0% Testing & commissioning Planned: 2026-08-08 → 2026-11-07 Forecast: 2026-12-25 → 2027-01-28 Float: 0d Drag to change its dates +82
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-28 0% Testing & acceptance complete Planned: 2026-11-07 → 2026-11-07 Forecast: 2027-01-28 → 2027-01-28 Float: 42d Drag to change its dates Testing & acceptance complete
5 Handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-03-11 0% Handover Planned: 2026-10-04 → 2027-02-28 Forecast: 2027-01-15 → 2027-03-11 Float: 0d
5.1 Provisional acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-18 0% Provisional acceptance Planned: 2026-10-04 → 2027-01-02 Forecast: 2027-01-15 → 2027-02-18 Float: 0d Drag to change its dates +47
5.2 Final acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-11 0% Final acceptance Planned: 2026-11-29 → 2027-02-28 Forecast: 2027-02-05 → 2027-03-11 Float: 0d Drag to change its dates +11
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-11 0% Final handover Planned: 2027-02-28 → 2027-02-28 Forecast: 2027-03-11 → 2027-03-11 Float: 0d Drag to change its dates Final handover