Latakia University Technical Engineering Faculty Extension
Add to watchlistA new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.
Budget (BAC)
Actual cost
53% of budget
Progress
Estimate at completion
+SYP 80.6M
SPI · CPI
Forecast finish
12 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure2 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-08-10 | 2025-11-04 | +86 days | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-02 | 2026-05-02 | +151 days | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-05-21 | 2026-11-26 | +189 days | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-07 | 2027-01-28 | +82 days | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-02-28 | 2027-03-11 | +11 days | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
52%Awaiting acceptance
11%Not handed in
37%Deliverable flow
Display options
| Project plan & baseline019-D1 | 4% | CRT-019-01 | Approved | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | Ibrahim Al-Saeed | 2025-06-15 | V1 | 3 of 3 |
| Monitoring & reporting019-D2 | 4% | CRT-019-02 | Approved | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2025-08-10 | V1 | 3 of 3 |
| Detailed design019-D3 | 7% | CRT-019-03 | Approved | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2025-10-06 | V1 | 3 of 3 |
| Permits & approvals019-D4 | 7% | CRT-019-04 | Approved | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Ibrahim Al-Saeed | 2025-12-02 | V1 | 3 of 3 |
| Site works & excavation019-D5 | 15% | CRT-019-05 | Approved | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Ibrahim Al-Saeed | 2026-01-27 | V1 | 3 of 3 |
| Structure019-D6 | 15% | CRT-019-06 | Approved | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | Ibrahim Al-Saeed | 2026-03-25 | V1 | 3 of 3 |
| Finishes019-D7 | 11% | — | Under review | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2026-05-21 | V1 | 1 of 3 |
| Supply019-D8 | 9% | — | Draft | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy | Ibrahim Al-Saeed | 2026-07-16 | V0 | 0 of 3 |
| Installation019-D9 | 8% | — | Draft | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2026-09-11 | V0 | 0 of 3 |
| Testing & commissioning019-D10 | 8% | — | Draft | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Ibrahim Al-Saeed | 2026-11-07 | V0 | 0 of 3 |
| Provisional acceptance019-D11 | 6% | — | Draft | Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.sy | Ibrahim Al-Saeed | 2027-01-02 | V0 | 0 of 3 |
| Final acceptance019-D12 | 6% | — | Draft | Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy | Ibrahim Al-Saeed | 2027-02-28 | V0 | 0 of 3 |
| Total · 12 | 100% |