PRJ-2026-019At risk4ExecutionConstructionIn progressDelivered by:Ministry of Higher Education and Scientific Research

Latakia University Technical Engineering Faculty Extension

Add to watchlist

A new building for the Faculty of Technical Engineering with labs, workshops and lecture halls — more places and trained technicians for the reconstruction projects.

Budget (BAC)

SYP 4B

Actual cost

SYP 2.1B

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 4B

+SYP 80.6M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
1On track
1At risk
1Late
Average delay104 days
Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27
Contractual
Build completePlanned: ⁦2026-05-21⁩Forecast / actual: ⁦2026-11-26⁩Delay: 189 daysG3 +189
Executive
Project plan approvedPlanned: ⁦2025-08-10⁩Forecast / actual: ⁦2025-11-04⁩Delay: 86 daysG1 +86
Payment
Final handoverPlanned: ⁦2027-02-28⁩Forecast / actual: ⁦2027-03-11⁩Delay: 11 daysG5 +11
Regulatory
Testing & acceptance completePlanned: ⁦2026-11-07⁩Forecast / actual: ⁦2027-01-28⁩Delay: 82 daysG4 +82
Project
Designs approvedPlanned: ⁦2025-12-02⁩Forecast / actual: ⁦2026-05-02⁩Delay: 151 daysG2 +151

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-08-10⁩⁦2025-11-04⁩⁦+86⁩ daysEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syAchieved1Approved
Designs approvedMS-G2Project⁦2025-12-02⁩⁦2026-05-02⁩⁦+151⁩ daysEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syAchieved1Approved
Build completeMS-G3Contractual⁦2026-05-21⁩⁦2026-11-26⁩⁦+189⁩ daysEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syLate0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2026-11-07⁩⁦2027-01-28⁩⁦+82⁩ daysEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syAt risk0Not requested
Final handoverMS-G5Payment⁦2027-02-28⁩⁦2027-03-11⁩⁦+11⁩ daysEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦52%⁩

Awaiting acceptance

⁦11%⁩

Not handed in

⁦37%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline019-D1⁦4%⁩CRT-019-01ApprovedEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syIbrahim Al-Saeed⁦2025-06-15⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting019-D2⁦4%⁩CRT-019-02ApprovedIbrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.syIbrahim Al-Saeed⁦2025-08-10⁩V1⁦3⁩ of ⁦3⁩
Detailed design019-D3⁦7%⁩CRT-019-03ApprovedIbrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.syIbrahim Al-Saeed⁦2025-10-06⁩V1⁦3⁩ of ⁦3⁩
Permits & approvals019-D4⁦7%⁩CRT-019-04ApprovedEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syIbrahim Al-Saeed⁦2025-12-02⁩V1⁦3⁩ of ⁦3⁩
Site works & excavation019-D5⁦15%⁩CRT-019-05ApprovedEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syIbrahim Al-Saeed⁦2026-01-27⁩V1⁦3⁩ of ⁦3⁩
Structure019-D6⁦15%⁩CRT-019-06ApprovedEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syIbrahim Al-Saeed⁦2026-03-25⁩V1⁦3⁩ of ⁦3⁩
Finishes019-D7⁦11%⁩—Under reviewIbrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.syIbrahim Al-Saeed⁦2026-05-21⁩V1⁦1⁩ of ⁦3⁩
Supply019-D8⁦9%⁩—DraftEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syIbrahim Al-Saeed⁦2026-07-16⁩V0⁦0⁩ of ⁦3⁩
Installation019-D9⁦8%⁩—DraftIbrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.syIbrahim Al-Saeed⁦2026-09-11⁩V0⁦0⁩ of ⁦3⁩
Testing & commissioning019-D10⁦8%⁩—DraftEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syIbrahim Al-Saeed⁦2026-11-07⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance019-D11⁦6%⁩—DraftIbrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesP-046ibrahim.alsaeed@psa.gov.syIbrahim Al-Saeed⁦2027-01-02⁩V0⁦0⁩ of ⁦3⁩
Final acceptance019-D12⁦6%⁩—DraftEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syIbrahim Al-Saeed⁦2027-02-28⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩
⁦1⁩–⁦12⁩ of ⁦12⁩