PRJ-2026-018At risk4ExecutionConstructionIn progressDelivered by:Ministry of Communications and Information Technology

Government Fibre Backbone — Damascus–Homs Segment

Add to watchlist

Laying a government fibre backbone between Damascus and Homs that links the ministries’ directorates and the main and backup data centres — the first segment of the network that will reach every governorate.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 3.3B

Actual cost

SYP 1.9B

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 3.4B

+SYP 102.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

Government Fibre Backbone — Damascus–Homs Segment

PRJ-2026-018 · Digital Transformation Sector · Operational · WP-2025-018

In progressAt risk4ExecutionProject manager: Eng. George Haddad · Sponsor: Eng. Khaled Al-Kayyali
Progress
⁦55%⁩ / ⁦63%⁩
SPI · CPI
0.87 · 0.97
Spend
SYP 1.9B / SYP 3.3B
Estimate at completion
SYP 3.4B

Schedule

⁦8%⁩ behind⁦55%⁩

Planned to date ⁦63%⁩

Forecast finish: 2027-03-05 · 33 days late

SPI0.87Schedule performance index · 0.87CPI0.97Cost performance index · 0.97

Health dimensions

At risk

Last update: 2026-09-21 · Update overdue

Deliverables

⁦6⁩ of ⁦10⁩ due deliverables accepted on time (⁦60%⁩)

Next milestones

  • Build complete2026-11-11
  • Testing & acceptance complete2027-01-16
  • Final handover2027-03-01

Top risks

  • City councils objecting to digging in built-up neighbourhoods12
  • Higher reinstatement costs after network trenching9

Open impediments

  • Digging permit suspended in Homs’s Al-Waer district · Open

Decisions and changes waiting

  • CR-2026-014 · Re-route the network in Homs’s Al-Waer district

Copilot summary

The scope holds 1 project with a budget of SYP 3.3bn: 0 on track and 0 red or critical. Weighted progress is 55% against 63% planned, spend SYP 1.87bn, and EAC SYP 3.4bn (SYP 102.1M over).

1 project is more than a month behind baseline; the worst: Government Fibre Backbone — Damascus–Homs Segment (33 days).

Planning and Statistics Authority · prepared by Eng. George Haddad in MunjazInternal

Status: At risk ·Project page