Project status card
28 October 2026
Government Fibre Backbone — Damascus–Homs Segment
PRJ-2026-018 · Digital Transformation Sector · Operational · WP-2025-018
- Progress
- 55% / 63%
- SPI · CPI
- 0.87 · 0.97
- Spend
- SYP 1.9B / SYP 3.3B
- Estimate at completion
- SYP 3.4B
Schedule
Planned to date 63%
Forecast finish: 2027-03-05 · 33 days late
SPI0.87Schedule performance index · 0.87CPI0.97Cost performance index · 0.97Health dimensions
Last update: 2026-09-21 · Update overdue
Deliverables
6 of 10 due deliverables accepted on time (60%)
Next milestones
- Build complete2026-11-11
- Testing & acceptance complete2027-01-16
- Final handover2027-03-01
Top risks
- City councils objecting to digging in built-up neighbourhoods12
- Higher reinstatement costs after network trenching9
Open impediments
- Digging permit suspended in Homs’s Al-Waer district · Open
Decisions and changes waiting
- CR-2026-014 · Re-route the network in Homs’s Al-Waer district
Copilot summary
The scope holds 1 project with a budget of SYP 3.3bn: 0 on track and 0 red or critical. Weighted progress is 55% against 63% planned, spend SYP 1.87bn, and EAC SYP 3.4bn (SYP 102.1M over).
1 project is more than a month behind baseline; the worst: Government Fibre Backbone — Damascus–Homs Segment (33 days).