PRJ-2026-016At risk4ExecutionWaterfallIn progressDelivered by:Planning and Statistics Authority

National Statistical Indicators & Open Data Portal

Add to watchlist

A portal publishing official statistical indicators for Syria and each governorate and opening the data to researchers and public bodies, with a data governance and classification policy.

Budget (BAC)

SYP 537.5M

Actual cost

SYP 350.8M

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 565.8M

+SYP 28.3M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-01-05⁩
ApprovedDMD-2026-016National Statistical Indicators & Open Data Portal

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-016
Project
National Statistical Indicators & Open Data Portal
Portfolio
Digital Government Services & Data Portfolio
Sector
Statistics Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Razan Al-Rifai

1The proposalAuto-filled

TitleAuto-filled
National Statistical Indicators & Open Data Portal
Proposed byAuto-filled
Razan Al-Rifai
DepartmentAuto-filled
National Indicators & Open Data Directorate
Submitted onAuto-filled
⁦2025-01-05⁩
Proposal numberAuto-filled
DMD-2026-016

2Justification

A portal publishing official statistical indicators for Syria and each governorate and opening the data to researchers and public bodies, with a data governance and classification policy.

3Objectives

  1. Reliable statistics and economic data for decisions

Strategic objectives served

  • SO-1.2 — Reliable statistics and economic data for decisions

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SYP 537.5M

Funding

The delivering body’s investment-plan allocations

Cost lineAmount
Main contractSYP 387.5M
Supervision & consultingSYP 75M
Internal teamSYP 47.5M
Contingency reserve (5%)SYP 27.5M
TotalSYP 537.5M

6Initial risks

RiskLevelProposed response
Too few accredited data owners in the ministries and governoratesMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Razan Al-RifaiDirector, Data & AISubmitted—⁦2025-01-05⁩ 09:36
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2025-01-06⁩ 13:16
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-01-09⁩ 14:23
4Portfolio manager reviewTechnical acceptanceBasel Al-MahayniPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-01-12⁩ 09:30
5Cost & funding reviewFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-01-13⁩ 09:12
6Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2025-01-16⁩ 11:44

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2025-01-06⁩

PMO review

Mariam Al-Zoubi

Approved⁦2025-01-09⁩

Portfolio manager review

Basel Al-Mahayni

Approved⁦2025-01-12⁩

Cost & funding review

Rasha Al-Mudarres

Approved⁦2025-01-13⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2025-01-16⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Razan Al-Rifai on ⁦2025-01-05⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2025-01-06⁩ at ⁦13:16⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-01-09⁩ at ⁦14:23⁩

  3. Technical acceptance

    Portfolio manager review

    Basel Al-Mahayni · Portfolio manager

    Approved · ⁦2025-01-12⁩ at ⁦09:30⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-01-13⁩ at ⁦09:12⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2025-01-16⁩ at ⁦11:44⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-01-26⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Razan Al-Rifai

  2. V1Returned for edit⁦2025-01-05⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Razan Al-Rifai