PRJ-2026-015On track4ExecutionScrumIn progressDelivered by:Ministry of Communications and Information Technology

Government Services Mobile App — New Release

Add to watchlist

The new release of the government services app: the most-used services, request tracking, notifications and bank e-payment.

Budget (BAC)

SYP 315M

Actual cost

SYP 193.8M

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 302.9M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
PSA-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2025-10-03⁩
ApprovedPRJ-2026-015Government Services Mobile App — New Release

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-015
Project
Government Services Mobile App — New Release
Portfolio
Digital Government Services & Data Portfolio
Sector
Local Development & Governorates Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Kinan Azzam

1Objective

Background

The new release of the government services app: the most-used services, request tracking, notifications and bank e-payment.

Project objectives

  1. Integrated digital government services for citizens

2Scope

In scope

  • The new release of the government services app: the most-used services, request tracking, notifications and bank e-payment.
  • Identity checks against the civil registry
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2025-10-24⁩
Main deliverable — stage 1⁦2026-06-08⁩
Main deliverable — final stage⁦2026-11-24⁩
Final report⁦2027-01-31⁩
MilestoneDate
Charter approved⁦2025-10-03⁩
Contract signed⁦2025-12-21⁩
50% of works complete⁦2026-06-08⁩
Provisional acceptance⁦2026-12-23⁩
Closure⁦2027-01-31⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Khaled Al-Kayyali
Project ownerAuto-filled
Basel Al-Mahayni
Project managerAuto-filled
Kinan Azzam
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
National Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSYP 227.5M
Supervision & consultingSYP 45M
Internal teamSYP 27.5M
Contingency reserve (5%)SYP 15M
Approved budgetSYP 315M

Funding

The delivering body’s investment-plan allocations

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the unified contracts law (Law 51 of 2004)

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Kinan AzzamSenior Digital Delivery Consultant — National PMOSubmitted—⁦2025-09-24⁩ 10:00
2PMO complianceMethodology reviewDr. Reem Al-QabbaniPMO — directorApproved—⁦2025-09-27⁩ 12:30
3Project ownerTechnical acceptanceBasel Al-MahayniProject ownerApproved—⁦2025-09-30⁩ 09:45
4Budget funding confirmedFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-10-01⁩ 11:10
5Sponsor approvalTechnical acceptanceEng. Khaled Al-KayyaliProject sponsorApproved—⁦2025-10-03⁩ 11:00

Signatures

PMO compliance

Dr. Reem Al-Qabbani

Approved⁦2025-09-27⁩

Project owner

Basel Al-Mahayni

Approved⁦2025-09-30⁩

Budget funding confirmed

Rasha Al-Mudarres

Approved⁦2025-10-01⁩

Sponsor approval

Eng. Khaled Al-Kayyali

Approved⁦2025-10-03⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Kinan Azzam on ⁦2025-09-24⁩

  1. Methodology review

    PMO compliance

    Dr. Reem Al-Qabbani · PMO — director

    Approved · ⁦2025-09-27⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Basel Al-Mahayni · Project owner

    Approved · ⁦2025-09-30⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-10-01⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Khaled Al-Kayyali · Project sponsor

    Approved · ⁦2025-10-03⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-10-03⁩

    Approved version

    • PMO comments addressed

    Kinan Azzam

  2. V1Returned for edit⁦2025-09-14⁩

    First draft

    • Returned to detail the budget

    Kinan Azzam

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close