PRJ-2026-015On track4ExecutionScrumIn progressDelivered by:Ministry of Communications and Information Technology

Government Services Mobile App — New Release

Add to watchlist

The new release of the government services app: the most-used services, request tracking, notifications and bank e-payment.

Budget (BAC)

SYP 315M

Actual cost

SYP 193.8M

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 302.9M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Project weight

The weight and the relative weight in the portfolio

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Approval

Project weight

The weight and the relative weight in the portfolio

Form no.
PSA-PMO-F03
Template edition
1.0
Version
V2
Form date
⁦2026-09-16⁩
ApprovedPRJ-2026-015Government Services Mobile App — New Release

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-015
Project
Government Services Mobile App — New Release
Portfolio
Digital Government Services & Data Portfolio
Sector
Local Development & Governorates Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Kinan Azzam

1Weight and relative weightAuto-filled

Project weight score

63 of 100

Relative weight in the portfolio

⁦15.6%⁩

Portfolio

Digital Government Services & Data Portfolio

7 projects

Its share of the portfolio’s progress

10.0 points of 61.1%

2Weight criteriaAuto-filled

Each criterion is rated 1–5 from the project’s record and multiplied by its approved weight.

CriterionRated fromWeightRatingPoints
Strategic importanceThe project’s strategic value⁦35%⁩428.0
Budget sizeApproved budget (BAC)⁦25%⁩15.0
Impact on citizens & beneficiariesThe project’s alignment score⁦20%⁩416.0
Complexity & riskThe project’s risk score⁦10%⁩24.0
Project classificationThe project’s classification⁦10%⁩510.0
Weight score—⁦100%⁩—63

3Relative weights across the portfolioAuto-filled

Proposed and cancelled projects are left out; suspended ones keep their frozen progress.

ProjectScoreRelative weightProgress
Unified Government e-Services Platform88⁦21.8%⁩⁦58%⁩
National Statistical Indicators & Open Data Portal70⁦17.3%⁩⁦62%⁩
Medium-Term Plan Implementation Tracker (ministries & governorates)66⁦16.3%⁩⁦1%⁩
e-Litigation & Judicial Notification Platform — Release 263⁦15.6%⁩⁦91%⁩
Government Services Mobile App — New Release63⁦15.6%⁩⁦64%⁩
Digital Signature & e-Verification of Government Documents — Phase 154⁦13.4%⁩⁦100%⁩
National Development & Reconstruction Forum 202759Not counted⁦0%⁩
Weighted portfolio progress—⁦100%⁩⁦61.1%⁩

Approval logChain: Project weight approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Mariam Al-ZoubiDirector, Education & Rural Development ProjectsSubmitted—⁦2026-09-16⁩ 14:11
2Weight model complianceMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-09-20⁩ 10:25
3Portfolio manager approvalTechnical acceptanceBasel Al-MahayniPortfolio managerApproved—⁦2026-09-23⁩ 11:32

Signatures

Weight model compliance

Mariam Al-Zoubi

Approved⁦2026-09-20⁩

Portfolio manager approval

Basel Al-Mahayni

Approved⁦2026-09-23⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F03 · version V2

Project weight

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project weight approval · version ⁦1⁩

Submitted by Mariam Al-Zoubi on ⁦2026-09-16⁩

  1. Methodology review

    Weight model compliance

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-09-20⁩ at ⁦10:25⁩

  2. Technical acceptance

    Portfolio manager approval

    Basel Al-Mahayni · Portfolio manager

    Approved · ⁦2026-09-23⁩ at ⁦11:32⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-09-14⁩

    Classification added at 10; budget cut from 35 to 25 so the building projects do not swamp the portfolio

    Dr. Reem Al-Qabbani

  2. V1Approved⁦2025-12-02⁩

    First model: strategic importance, budget, impact, complexity

    Dr. Reem Al-Qabbani