PRJ-2026-013At risk4ExecutionConstructionIn progressDelivered by:Ministry of Transport

Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals

Add to watchlist

Solar lighting for the highway between As-Sanamayn and Daraa: 1,200 lighting poles and traffic cameras, smart signals at the junctions and a traffic control room in Daraa.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 1.9B

Actual cost

SYP 1.6B

⁦84%⁩ of budget

Progress

⁦79%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 2B

+SYP 118.1M

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure11 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP1.8B⁦17⁩ elements
Unallocated contingencySYP55.5MSYP 92.5M
Budget at completionSYP1.9BPRJ-2026-013
Weighted progress⁦79%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project694⁦2025-02-16⁩⁦2027-01-11⁩⁦79%⁩1,794.501,554.79—
1
Phase168⁦2025-02-16⁩⁦2025-08-03⁩⁦100%⁩107.67118.09—
1.1
WBS element103⁦2025-02-16⁩⁦2025-05-30⁩⁦100%⁩53.8459.040 / 1
1.2
WBS element104⁦2025-04-21⁩⁦2025-08-03⁩⁦100%⁩53.8459.041 / 2
2
Phase168⁦2025-06-25⁩⁦2025-12-10⁩⁦100%⁩215.34236.17—
2.1
WBS element103⁦2025-06-25⁩⁦2025-10-06⁩⁦100%⁩107.67118.091 / 1
2.2
WBS element104⁦2025-08-28⁩⁦2025-12-10⁩⁦100%⁩107.67118.091 / 2
3
Phase232⁦2025-11-01⁩⁦2026-06-21⁩⁦100%⁩681.91747.87—
3.1
WBS element103⁦2025-11-01⁩⁦2026-02-12⁩⁦100%⁩227.30249.291 / 1
3.2
WBS element103⁦2026-01-04⁩⁦2026-04-17⁩⁦100%⁩227.30249.291 / 1
3.3
WBS element103⁦2026-03-10⁩⁦2026-06-21⁩⁦100%⁩227.30249.291 / 2
4
Phase230⁦2026-05-06⁩⁦2026-12-22⁩⁦77%⁩538.35452.66—
4.1
WBS element103⁦2026-05-13⁩⁦2026-08-24⁩⁦100%⁩179.45196.811 / 1
4.2
WBS element101⁦2026-07-17⁩⁦2026-10-26⁩⁦100%⁩179.45196.811 / 1
4.3
WBS element230⁦2026-05-06⁩⁦2026-12-22⁩⁦30%⁩179.4559.041 / 2
5
Phase26⁦2026-12-16⁩⁦2027-01-11⁩⁦0%⁩251.23——
5.1
WBS element16⁦2026-12-16⁩⁦2027-01-01⁩⁦0%⁩125.62—1 / 1
5.2
WBS element16⁦2026-12-26⁩⁦2027-01-11⁩⁦0%⁩125.62—1 / 1
Total⁦79%⁩1,794.501,554.79