PRJ-2026-011On track3PlanningWaterfallNot startedDelivered by:Ministry of Interior
Civil Registry Automation & Governorate Link-up
Add to watchlist
Digitising civil-registry records and linking the governorate civil-registry offices to one database — the identity check behind every government e-service.
1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Forecast finish
2027-12-30
On baseline
Planning·Stage 3 of 5
Next gate:Execution30 September 2026
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Project plan & baselinePlanned: 2026-07-05 → 2026-09-18Actual: 2026-07-05 → 2026-10-26
2026-12-0450%
Monitoring & reportingPlanned: 2026-08-21 → 2026-11-04Forecast: 2026-08-21 → 2026-12-04Float: 0dDrag to change its duration+30
2026-12-040%
Project plan approvedPlanned: 2026-11-04 → 2026-11-04Forecast: 2026-12-04 → 2026-12-04Float: 396dDrag to change its datesProject plan approved