Kick-off meeting minutes
Roles, tasks, decisions and the start of execution
- Form no.
- PSA-PMO-F06
- Template edition
- 1.2
- Version
- V1
- Form date
- 2024-02-11
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-007
- Project
- Hama National Hospital Upgrade & Extension
- Portfolio
- Health, Education & Industrial Recovery Portfolio
- Sector
- Development Projects Follow-up Sector
- Sponsor
- Eng. Abdulrahman Al-Kilani
- Project manager
- Eng. Sara Al-Barazi
1The meetingAuto-filled
- MeetingAuto-filled
- Kick-off — Hama National Hospital Upgrade & Extension
- Date and timeAuto-filled
- 2024-02-11 · 10:00
- PlaceAuto-filled
- Main meeting room — Authority HQ, Kafr Sousa
- SecretaryAuto-filled
- Eng. Sara Al-Barazi
Purpose
Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.
| Attendees | Title |
|---|---|
| Eng. Abdulrahman Al-Kilani | Deputy President, Development Projects Follow-up |
| Eng. Fadi Al-Droubi | Director General, Human Development Projects |
| Eng. Sara Al-Barazi | Senior Project Manager — Hospitals & Health Facilities |
| Dr. Reem Al-Qabbani | Director, National Project Management Office |
| Eng. Fadi Al-Droubi | Director General, Human Development Projects |
| Omar Al-Nahhas | Senior Finance & Contracts Specialist |
| Eng. Adnan Al-Mohammad | Senior Site Engineer (Contractor) |
2Roles
| Person | Role | Duty |
|---|---|---|
| Eng. Abdulrahman Al-Kilani | Project sponsor | Sponsors the project, decides escalations and material changes |
| Eng. Fadi Al-Droubi | Project owner | Approves the requirements and accepts the deliverables |
| Eng. Sara Al-Barazi | Project manager | Runs the plan, deliverables and risks; files the periodic update card |
| Dr. Reem Al-Qabbani | Project Management Office | Follows the methodology and checks the periodic updates |
| Eng. Fadi Al-Droubi | Project owner | Delivers their tasks and uploads the evidence |
| Omar Al-Nahhas | Hama hospital extension contract & certificates | Delivers their tasks and uploads the evidence |
| Eng. Adnan Al-Mohammad | Site engineer (MEP) | Delivers their tasks and uploads the evidence |
3Tasks
| Task | Owner | Due | Status |
|---|---|---|---|
| Project plan approved | Eng. Sara Al-Barazi | 2024-09-10 | Done |
| Designs approved | Eng. Sara Al-Barazi | 2025-02-25 | Done |
| Build complete | Eng. Sara Al-Barazi | 2025-11-05 | Done |
| Testing & acceptance complete | Eng. Sara Al-Barazi | 2026-07-16 | Open |
4Decisions
- The charter is the reference for scope, budget and the milestone plan
- Change Committee: Approves scope, cost and schedule changes (Weekly)
- Project Approval Committee: Methodology compliance, data quality, stage gates (Fortnightly)
- The periodic update card monthly, before the 5th of the month
5Start of execution
- Execution starts on
- 2024-07-23
- Start confirmed
- Eng. Abdulrahman Al-Kilani · 2024-02-12
Approval logChain: Kick-off minutes approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Sara Al-BaraziSenior Project Manager — Hospitals & Health Facilities | Submitted | — | 2024-02-12 12:03 |
| 2 | Chair’s approval (sponsor) | Technical acceptance | Eng. Abdulrahman Al-KilaniProject sponsor | Approved | — | 2024-02-13 12:30 |
| 3 | Minutes against the template | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | — | 2024-02-14 10:37 |
Signatures
Minutes against the template
Mariam Al-Zoubi
Approved2024-02-14
Chair’s approval (sponsor)
Eng. Abdulrahman Al-Kilani
Approved2024-02-13