PRJ-2026-007Critical4ExecutionConstructionStalledDelivered by:Ministry of Health

Hama National Hospital Upgrade & Extension

Remove from watchlist

Extending Hama National Hospital with a new wing of 42 wards and theatres and upgrading its medical equipment, running 9 temporary wards so care never stops during the works.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 16B

Actual cost

SYP 11.1B

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 19.5B

+SYP 3.5B

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Project weight

The weight and the relative weight in the portfolio

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Approval

Project weight

The weight and the relative weight in the portfolio

Form no.
PSA-PMO-F03
Template edition
1.0
Version
V2
Form date
⁦2026-09-16⁩
ApprovedPRJ-2026-007Hama National Hospital Upgrade & Extension

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-007
Project
Hama National Hospital Upgrade & Extension
Portfolio
Health, Education & Industrial Recovery Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Eng. Abdulrahman Al-Kilani
Project manager
Eng. Sara Al-Barazi

1Weight and relative weightAuto-filled

Project weight score

89 of 100

Relative weight in the portfolio

⁦27.3%⁩

Portfolio

Health, Education & Industrial Recovery Portfolio

4 projects

Its share of the portfolio’s progress

15.6 points of 38.4%

2Weight criteriaAuto-filled

Each criterion is rated 1–5 from the project’s record and multiplied by its approved weight.

CriterionRated fromWeightRatingPoints
Strategic importanceThe project’s strategic value⁦35%⁩428.0
Budget sizeApproved budget (BAC)⁦25%⁩525.0
Impact on citizens & beneficiariesThe project’s alignment score⁦20%⁩416.0
Complexity & riskThe project’s risk score⁦10%⁩510.0
Project classificationThe project’s classification⁦10%⁩510.0
Weight score—⁦100%⁩—89

3Relative weights across the portfolioAuto-filled

Proposed and cancelled projects are left out; suspended ones keep their frozen progress.

ProjectScoreRelative weightProgress
Hama National Hospital Upgrade & Extension89⁦27.3%⁩⁦57%⁩
Sheikh Najjar Industrial City Rehabilitation82⁦25.2%⁩⁦39%⁩
Latakia University Technical Engineering Faculty Extension80⁦24.5%⁩⁦52%⁩
Al-Mayadin General Hospital75⁦23.0%⁩⁦1%⁩
Weighted portfolio progress—⁦100%⁩⁦38.4%⁩

Approval logChain: Project weight approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Mariam Al-ZoubiDirector, Education & Rural Development ProjectsSubmitted—⁦2026-09-16⁩ 09:48
2Weight model complianceMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-09-17⁩ 11:32
3Portfolio manager approvalTechnical acceptanceEng. Fadi Al-DroubiPortfolio managerApproved—⁦2026-09-20⁩ 12:39

Signatures

Weight model compliance

Mariam Al-Zoubi

Approved⁦2026-09-17⁩

Portfolio manager approval

Eng. Fadi Al-Droubi

Approved⁦2026-09-20⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F03 · version V2

Project weight

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project weight approval · version ⁦1⁩

Submitted by Mariam Al-Zoubi on ⁦2026-09-16⁩

  1. Methodology review

    Weight model compliance

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-09-17⁩ at ⁦11:32⁩

  2. Technical acceptance

    Portfolio manager approval

    Eng. Fadi Al-Droubi · Portfolio manager

    Approved · ⁦2026-09-20⁩ at ⁦12:39⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-09-14⁩

    Classification added at 10; budget cut from 35 to 25 so the building projects do not swamp the portfolio

    Dr. Reem Al-Qabbani

  2. V1Approved⁦2025-12-02⁩

    First model: strategic importance, budget, impact, complexity

    Dr. Reem Al-Qabbani