Government Network Cybersecurity Programme
Add to watchlistA round-the-clock security operations centre, identity and access protection, penetration testing and higher compliance of government bodies with the national cybersecurity controls.
Budget (BAC)
Actual cost
85% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure22 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-07-05 | 2025-07-23 | +18 days | Eng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-10-30 | 2025-12-02 | +33 days | Eng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-04-24 | 2026-06-18 | +55 days | Eng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.sy | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-08-20 | 2026-10-26 | +67 days | Eng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.sy | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2026-12-15 | 2027-01-02 | +18 days | Eng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.sy | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
88%Awaiting acceptance
6%Not handed in
6%Deliverable flow
Display options
| Project plan & baseline005-D1 | 4% | CRT-005-01 | Approved | Eng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.sy | Eng. Mazen Kassab | 2025-05-07 | V1 | 3 of 3 |
| Monitoring & reporting005-D2 | 4% | CRT-005-02 | Approved | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2025-07-05 | V1 | 3 of 3 |
| Business requirements005-D3 | 9% | CRT-005-03 | Approved | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2025-09-01 | V1 | 3 of 3 |
| Solution design005-D4 | 9% | CRT-005-04 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mazen Kassab | 2025-10-30 | V1 | 3 of 3 |
| Release 1005-D5 | 14% | CRT-005-05 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mazen Kassab | 2025-12-28 | V1 | 3 of 3 |
| Release 2005-D6 | 14% | CRT-005-06 | Approved | Eng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.sy | Eng. Mazen Kassab | 2026-02-24 | V1 | 3 of 3 |
| Integrations005-D7 | 14% | CRT-005-07 | Approved | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2026-04-24 | V1 | 3 of 3 |
| System testing005-D8 | 10% | CRT-005-08 | Approved | Eng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.sy | Eng. Mazen Kassab | 2026-06-22 | V1 | 3 of 3 |
| User acceptance testing005-D9 | 10% | CRT-005-09 | Approved | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2026-08-20 | V1 | 3 of 3 |
| Training & change005-D10 | 6% | — | Submitted | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2026-10-17 | V1 | 1 of 3 |
| Go-live & handover005-D11 | 6% | — | Draft | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mazen Kassab | 2026-12-15 | V0 | 0 of 3 |
| Total · 11 | 100% |