Project status card
28 October 2026
Government Backup Data Centre, Homs — Phase 2
PRJ-2026-003 · Digital Transformation Sector · Operational · WP-2025-003
- Progress
- 72% / 80%
- SPI · CPI
- 0.90 · 0.91
- Spend
- SYP 2.9B / SYP 3.7B
- Estimate at completion
- SYP 4.1B
Schedule
Planned to date 80%
Forecast finish: 2027-01-07 · 38 days late
SPI0.90Schedule performance index · 0.90CPI0.91Cost performance index · 0.91Health dimensions
Last update: 2026-10-22 · Up to date
Deliverables
6 of 10 due deliverables accepted on time (60%)
Next milestones
- Testing & acceptance complete2026-12-08
- Final handover2027-01-09
Top risks
- Exchange-rate swings on imported equipment with unfixed prices16
- Late delivery of cooling units and standby generators12
Open impediments
- Cooling units shipment held at Latakia port · Open
Decisions and changes waiting
- Review certificate 13 — Homs backup data centre
Copilot summary
The scope holds 1 project with a budget of SYP 3.7bn: 0 on track and 0 red or critical. Weighted progress is 72% against 80% planned, spend SYP 2.93bn, and EAC SYP 4.07bn (SYP 365.9M over).
1 project is more than a month behind baseline; the worst: Government Backup Data Centre, Homs — Phase 2 (38 days).