PRJ-2026-007 · From item 2
Hama National Hospital Upgrade & ExtensionPlanned to date 82%
- SPI
- 0.70
- Forecast finish
- 2027-06-01
- Budget
- SYP 16B
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
Change requests with complete files, week 43.
Held on
21 October 202613:00 – 14:10
60 of 60 min
Approve the previous minutes
ApprovalEng. Wael Al-Khawlani
5 min
Hama hospital — 150-day extension
DecisionEng. Sara Al-Barazi
30 min
Douma treatment plant — axes 12–16 foundation redesign
DecisionEng. Qasem Al-Hariri
25 min
1. Approve the previous minutes
Meeting 40 minutes approved.
2. Hama hospital — 150-day extension
CR-2026-006Deferred pending the independent engineer; Finance abstained.
3. Douma treatment plant — axes 12–16 foundation redesign
CR-2026-010At SYP 210M on a revised baseline it exceeds the change committee’s authority; sent up to the national projects steering committee.
Voting rule: Simple majority; a Finance objection on impact above SYP 125M sends it to the national steering committee
Hama hospital extension decision deferred pending the independent engineer
DEC-2026-040Hold
For 4Against 0Abstain 1Carried
They show in the task register and on the owner’s calendar
No tasks from this meeting yet
Quorum: Four of six members, including Finance
At least 4 voting members needed
2 files
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-007 · From item 2
Hama National Hospital Upgrade & ExtensionPlanned to date 82%
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
PRJ-2026-020 · From item 3
Douma Wastewater Treatment PlantPlanned to date 55%
64 days lateMaterial risks: 1Open impediments: 1Corrective plan CP-2026-04
Agenda item needing a decision · CR-2026-006
Hama hospital — 150-day extensionFrom item 2
Agenda item needing a decision · CR-2026-010
Douma treatment plant — axes 12–16 foundation redesignFrom item 3
Change request awaiting decision · CR-2026-005
Change order 7: medical gases and HVAC redesignHama National Hospital Upgrade & Extension
Corrective plan awaiting approval · CP-2026-03
Hama National Hospital Upgrade & ExtensionISS-0109 · Hama National Hospital Upgrade & Extension
A decision· Asked from: Authority Executive Council
A decision to accept an equivalent finishing material on the consultant’s advice, or to extend the supply period
CP-2026-03 · Hama National Hospital Upgrade & Extension
A decision· Asked from: Authority Executive Council
A decision to accept an equivalent finishing material on the consultant’s advice
ACT-0311 · Eng. Wael Al-Khawlani