PSA/2025/023
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
55% of the current value paid
Paid
SYP1.6Bof a current value of SYP 3B
Value of each certificate
The last 11 — gross and net
Approved: 10
Count: 11 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | Net | Status | |
|---|---|---|---|---|---|---|---|
| Certificate 11September 2026 | 2026-10-18 | SYP127.5M | SYP12.8M | SYP12.8M | SYP102M | In review | |
| Certificate 10August 2026 | 2026-09-16 | SYP86.5M | SYP8.7M | SYP8.7M | SYP69.2M | Approved | |
| Certificate 9July 2026 | 2026-07-24 | SYP127M | SYP12.7M | SYP12.7M | SYP101.6M | Approved | |
| Certificate 8May 2026 | 2026-06-01 | SYP166.8M | SYP16.7M | SYP16.7M | SYP133.4M | Approved | |
| Certificate 7March 2026 | 2026-04-08 | SYP224.3M | SYP22.4M | SYP22.4M | SYP179.4M | Approved | |
| Certificate 6January 2026 | 2026-02-13 | SYP198M | SYP19.8M | SYP19.8M | SYP158.4M | Approved | |
| Certificate 5December 2025 | 2025-12-22 | SYP224.8M | SYP22.5M | SYP22.5M | SYP179.8M | Approved | |
| Certificate 4October 2025 | 2025-10-29 | SYP216M | SYP21.6M | SYP21.6M | SYP172.8M | Approved | |
| Certificate 3August 2025 | 2025-09-05 | SYP156M | SYP15.6M | SYP15.6M | SYP124.8M | Approved | |
| Certificate 2June 2025 | 2025-07-14 | SYP140.3M | SYP14M | SYP14M | SYP112.2M | Approved | |
| Certificate 1May 2025 | 2025-05-21 | SYP83M | SYP8.3M | SYP8.3M | SYP66.4M | Approved |