Certificate ⁦4⁩ — October 2025

Latakia University technical engineering faculty — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
4
Date
⁦2025-10-29⁩
Reference
PAY-2025-023-04

Interim payment certificate no. (⁦4⁩)

For the work of October 2025

Contract number
PSA/2025/023
Tender file no.
2504720693
Contract
Latakia University technical engineering faculty — construction
Contractor
Al-Sahel Contracting & Development Co.
Contractor tax number
TX-437644
Project
Latakia University Technical Engineering Faculty Extension
Contract period
⁦2025-04-06⁩ — ⁦2027-02-28⁩
Original contract value
SYP2,950,000,000
Current contract value
SYP2,950,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date595,250,000
2Less: previous certificates(379,250,000)
3Value of work in this certificate216,000,000
4Less: retention (⁦10%⁩)(21,600,000)
5Less: advance payment recovery (⁦10%⁩)(21,600,000)
6Less: delay and breach penalties0
7Total deductions(43,200,000)
8Net amount payable to the contractorSYP172,800,000

Amount in words: One hundred seventy-two million eight hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 59.5M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation206,500,00063,200,00032,950,00096,150,000⁦47%⁩
Earthworks & foundations531,000,00097,800,00052,200,000150,000,000⁦28%⁩
Concrete & structural works914,500,000129,100,00073,875,000202,975,000⁦22%⁩
Mechanical, electrical & plumbing708,000,00061,475,00038,525,000100,000,000⁦14%⁩
Finishes & external works442,500,00024,150,00016,025,00040,175,000⁦9%⁩
Testing & commissioning147,500,0003,525,0002,425,0005,950,000⁦4%⁩
Total2,950,000,000379,250,000216,000,000595,250,000⁦20%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ali Deeb

Deeb⁦2025-10-29⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-10-31⁩

Project manager

Eng. Youssef Shehabi

Shehabi⁦2025-11-03⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-11-06⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-11-09⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-10-29⁩

    Eng. Ali Deeb

  2. Engineer verifies quantities⁦2025-10-31⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-11-03⁩

    Eng. Youssef Shehabi · Senior Project Manager — Governorate Projects

    Took 3 days

  4. Payment order prepared⁦2025-11-06⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-11-09⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-04-22⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Youssef Shehabi → Dr. Samer Al-Daqqar

Certificate history

9 November 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-11-09 13:00

6 November 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-11-06 13:00

3 November 2025

  1. Approval: Eng. Youssef Shehabi signed “Project manager certifies”

    2025-11-03 13:00

31 October 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-10-31 13:00

29 October 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-10-29 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close