Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 3
- Date
- 2025-09-05
- Reference
- PAY-2025-023-03
Interim payment certificate no. (3)
For the work of August 2025
- Contract number
- PSA/2025/023
- Tender file no.
- 2504720693
- Contract
- Latakia University technical engineering faculty — construction
- Contractor
- Al-Sahel Contracting & Development Co.
- Contractor tax number
- TX-437644
- Project
- Latakia University Technical Engineering Faculty Extension
- Contract period
- 2025-04-06 — 2027-02-28
- Original contract value
- SYP2,950,000,000
- Current contract value
- SYP2,950,000,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SYP)
| 1 | Total value of work completed to date | 379,250,000 |
| 2 | Less: previous certificates | (223,250,000) |
| 3 | Value of work in this certificate | 156,000,000 |
| 4 | Less: retention (10%) | (15,600,000) |
| 5 | Less: advance payment recovery (10%) | (15,600,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (31,200,000) |
| 8 | Net amount payable to the contractor | SYP124,800,000 |
Amount in words: One hundred twenty-four million eight hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 37.9M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 206,500,000 | 36,875,000 | 24,350,000 | 61,225,000 | 30% |
| Earthworks & foundations | 531,000,000 | 57,225,000 | 38,350,000 | 95,575,000 | 18% |
| Concrete & structural works | 914,500,000 | 76,025,000 | 53,300,000 | 129,325,000 | 14% |
| Mechanical, electrical & plumbing | 708,000,000 | 36,550,000 | 27,175,000 | 63,725,000 | 9% |
| Finishes & external works | 442,500,000 | 14,450,000 | 11,150,000 | 25,600,000 | 6% |
| Testing & commissioning | 147,500,000 | 2,125,000 | 1,675,000 | 3,800,000 | 3% |
| Total | 2,950,000,000 | 223,250,000 | 156,000,000 | 379,250,000 | 13% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Ali Deeb
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Youssef Shehabi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar