Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 7
- Date
- 2026-04-08
- Reference
- PAY-2025-023-07
Interim payment certificate no. (7)
For the work of March 2026
- Contract number
- PSA/2025/023
- Tender file no.
- 2504720693
- Contract
- Latakia University technical engineering faculty — construction
- Contractor
- Al-Sahel Contracting & Development Co.
- Contractor tax number
- TX-437644
- Project
- Latakia University Technical Engineering Faculty Extension
- Contract period
- 2025-04-06 — 2027-02-28
- Original contract value
- SYP2,950,000,000
- Current contract value
- SYP2,950,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 1,242,250,000 |
| 2 | Less: previous certificates | (1,018,000,000) |
| 3 | Value of work in this certificate | 224,250,000 |
| 4 | Less: retention (10%) | (22,425,000) |
| 5 | Less: advance payment recovery (10%) | (22,425,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (44,850,000) |
| 8 | Net amount payable to the contractor | SYP179,400,000 |
Amount in words: One hundred seventy-nine million four hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 124.2M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 206,500,000 | 169,550,000 | 31,075,000 | 200,625,000 | 97% |
| Earthworks & foundations | 531,000,000 | 262,450,000 | 50,600,000 | 313,050,000 | 59% |
| Concrete & structural works | 914,500,000 | 346,550,000 | 77,050,000 | 423,600,000 | 46% |
| Mechanical, electrical & plumbing | 708,000,000 | 165,125,000 | 43,575,000 | 208,700,000 | 29% |
| Finishes & external works | 442,500,000 | 64,925,000 | 18,925,000 | 83,850,000 | 19% |
| Testing & commissioning | 147,500,000 | 9,400,000 | 3,025,000 | 12,425,000 | 8% |
| Total | 2,950,000,000 | 1,018,000,000 | 224,250,000 | 1,242,250,000 | 42% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Ali Deeb
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Youssef Shehabi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar