Certificate ⁦6⁩ — January 2026

Latakia University technical engineering faculty — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
6
Date
⁦2026-02-13⁩
Reference
PAY-2025-023-06

Interim payment certificate no. (⁦6⁩)

For the work of January 2026

Contract number
PSA/2025/023
Tender file no.
2504720693
Contract
Latakia University technical engineering faculty — construction
Contractor
Al-Sahel Contracting & Development Co.
Contractor tax number
TX-437644
Project
Latakia University Technical Engineering Faculty Extension
Contract period
⁦2025-04-06⁩ — ⁦2027-02-28⁩
Original contract value
SYP2,950,000,000
Current contract value
SYP2,950,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date1,018,000,000
2Less: previous certificates(820,000,000)
3Value of work in this certificate198,000,000
4Less: retention (⁦10%⁩)(19,800,000)
5Less: advance payment recovery (⁦10%⁩)(19,800,000)
6Less: delay and breach penalties0
7Total deductions(39,600,000)
8Net amount payable to the contractorSYP158,400,000

Amount in words: One hundred fifty-eight million four hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 101.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation206,500,000135,875,00028,525,000164,400,000⁦80%⁩
Earthworks & foundations531,000,000210,600,00045,925,000256,525,000⁦48%⁩
Concrete & structural works914,500,000279,250,00067,900,000347,150,000⁦38%⁩
Mechanical, electrical & plumbing708,000,000133,775,00037,250,000171,025,000⁦24%⁩
Finishes & external works442,500,00052,800,00015,925,00068,725,000⁦16%⁩
Testing & commissioning147,500,0007,700,0002,475,00010,175,000⁦7%⁩
Total2,950,000,000820,000,000198,000,0001,018,000,000⁦35%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ali Deeb

Deeb⁦2026-02-13⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-02-15⁩

Project manager

Eng. Youssef Shehabi

Shehabi⁦2026-02-18⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-02-21⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-02-24⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-02-13⁩

    Eng. Ali Deeb

  2. Engineer verifies quantities⁦2026-02-15⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-02-18⁩

    Eng. Youssef Shehabi · Senior Project Manager — Governorate Projects

    Took 3 days

  4. Payment order prepared⁦2026-02-21⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-02-24⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-04-22⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Youssef Shehabi → Dr. Samer Al-Daqqar

Certificate history

24 February 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-02-24 13:00

21 February 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-02-21 13:00

18 February 2026

  1. Approval: Eng. Youssef Shehabi signed “Project manager certifies”

    2026-02-18 13:00

15 February 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-02-15 13:00

13 February 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-02-13 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close