Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 6
- Date
- 2026-02-13
- Reference
- PAY-2025-023-06
Interim payment certificate no. (6)
For the work of January 2026
- Contract number
- PSA/2025/023
- Tender file no.
- 2504720693
- Contract
- Latakia University technical engineering faculty — construction
- Contractor
- Al-Sahel Contracting & Development Co.
- Contractor tax number
- TX-437644
- Project
- Latakia University Technical Engineering Faculty Extension
- Contract period
- 2025-04-06 — 2027-02-28
- Original contract value
- SYP2,950,000,000
- Current contract value
- SYP2,950,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 1,018,000,000 |
| 2 | Less: previous certificates | (820,000,000) |
| 3 | Value of work in this certificate | 198,000,000 |
| 4 | Less: retention (10%) | (19,800,000) |
| 5 | Less: advance payment recovery (10%) | (19,800,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (39,600,000) |
| 8 | Net amount payable to the contractor | SYP158,400,000 |
Amount in words: One hundred fifty-eight million four hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 101.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 206,500,000 | 135,875,000 | 28,525,000 | 164,400,000 | 80% |
| Earthworks & foundations | 531,000,000 | 210,600,000 | 45,925,000 | 256,525,000 | 48% |
| Concrete & structural works | 914,500,000 | 279,250,000 | 67,900,000 | 347,150,000 | 38% |
| Mechanical, electrical & plumbing | 708,000,000 | 133,775,000 | 37,250,000 | 171,025,000 | 24% |
| Finishes & external works | 442,500,000 | 52,800,000 | 15,925,000 | 68,725,000 | 16% |
| Testing & commissioning | 147,500,000 | 7,700,000 | 2,475,000 | 10,175,000 | 7% |
| Total | 2,950,000,000 | 820,000,000 | 198,000,000 | 1,018,000,000 | 35% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Ali Deeb
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Youssef Shehabi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar