Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦8⁩ — May 2026

Latakia University technical engineering faculty — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
8
Date
⁦2026-06-01⁩
Reference
PAY-2025-023-08

Interim payment certificate no. (⁦8⁩)

For the work of May 2026

Contract number
PSA/2025/023
Tender file no.
2504720693
Contract
Latakia University technical engineering faculty — construction
Contractor
Al-Sahel Contracting & Development Co.
Contractor tax number
TX-437644
Project
Latakia University Technical Engineering Faculty Extension
Contract period
⁦2025-04-06⁩ — ⁦2027-02-28⁩
Original contract value
SYP2,950,000,000
Current contract value
SYP2,950,000,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date1,409,000,000
2Less: previous certificates(1,242,250,000)
3Value of work in this certificate166,750,000
4Less: retention (⁦10%⁩)(16,675,000)
5Less: advance payment recovery (⁦10%⁩)(16,675,000)
6Less: delay and breach penalties0
7Total deductions(33,350,000)
8Net amount payable to the contractorSYP133,400,000

Amount in words: One hundred thirty-three million four hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 140.9M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation206,500,000186,250,00020,250,000206,500,000⁦100%⁩
Earthworks & foundations531,000,000337,225,00038,900,000376,125,000⁦71%⁩
Concrete & structural works914,500,000423,150,00057,325,000480,475,000⁦53%⁩
Mechanical, electrical & plumbing708,000,000203,425,00033,275,000236,700,000⁦33%⁩
Finishes & external works442,500,00080,475,00014,625,00095,100,000⁦21%⁩
Testing & commissioning147,500,00011,725,0002,375,00014,100,000⁦10%⁩
Total2,950,000,0001,242,250,000166,750,0001,409,000,000⁦48%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ali Deeb

Deeb⁦2026-06-01⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-06-03⁩

Project manager

Eng. Youssef Shehabi

Shehabi⁦2026-06-06⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-06-09⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-06-12⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-06-01⁩

    Eng. Ali Deeb

  2. Engineer verifies quantities⁦2026-06-03⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-06-06⁩

    Eng. Youssef Shehabi · Senior Project Manager — Governorate Projects

    Took 3 days

  4. Payment order prepared⁦2026-06-09⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-06-12⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-09-29⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Youssef Shehabi → Dr. Samer Al-Daqqar

Certificate history

12 June 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-06-12 13:00

9 June 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-06-09 13:00

6 June 2026

  1. Approval: Eng. Youssef Shehabi signed “Project manager certifies”

    2026-06-06 13:00

3 June 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-06-03 13:00

1 June 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-06-01 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close