Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦4⁩ — December 2025

Government fibre backbone roll-out — Damascus–Homs segment

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
4
Date
⁦2026-01-10⁩
Reference
PAY-2025-020-04

Interim payment certificate no. (⁦4⁩)

For the work of December 2025

Contract number
PSA/2025/020
Tender file no.
2504510654
Contract
Government fibre backbone roll-out — Damascus–Homs segment
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Government Fibre Backbone — Damascus–Homs Segment
Contract period
⁦2025-06-01⁩ — ⁦2027-01-31⁩
Original contract value
SYP2,700,000,000
Current contract value
SYP2,700,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date687,750,000
2Less: previous certificates(443,500,000)
3Value of work in this certificate244,250,000
4Less: retention (⁦10%⁩)(24,425,000)
5Less: advance payment recovery (⁦10%⁩)(24,425,000)
6Less: delay and breach penalties0
7Total deductions(48,850,000)
8Net amount payable to the contractorSYP195,400,000

Amount in words: One hundred ninety-five million four hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 68.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation189,000,00074,525,00036,525,000111,050,000⁦59%⁩
Earthworks & foundations486,000,000115,100,00058,225,000173,325,000⁦36%⁩
Concrete & structural works837,000,000150,900,00083,625,000234,525,000⁦28%⁩
Mechanical, electrical & plumbing648,000,00071,175,00044,375,000115,550,000⁦18%⁩
Finishes & external works405,000,00027,800,00018,625,00046,425,000⁦11%⁩
Testing & commissioning135,000,0004,000,0002,875,0006,875,000⁦5%⁩
Total2,700,000,000443,500,000244,250,000687,750,000⁦25%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2026-01-10⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-01-12⁩

Project manager

Eng. George Haddad

Haddad⁦2026-01-15⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-01-18⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-01-21⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-01-10⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2026-01-12⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-01-15⁩

    Eng. George Haddad · Director, Data Centres & Government Network

    Took 3 days

  4. Payment order prepared⁦2026-01-18⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-01-21⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-05-02⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. George Haddad → Dr. Samer Al-Daqqar

Certificate history

21 January 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-01-21 13:00

18 January 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-01-18 13:00

15 January 2026

  1. Approval: Eng. George Haddad signed “Project manager certifies”

    2026-01-15 13:00

12 January 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-01-12 13:00

10 January 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-01-10 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close