Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 4
- Date
- 2026-01-10
- Reference
- PAY-2025-020-04
Interim payment certificate no. (4)
For the work of December 2025
- Contract number
- PSA/2025/020
- Tender file no.
- 2504510654
- Contract
- Government fibre backbone roll-out — Damascus–Homs segment
- Contractor
- Modern Networks Telecom Co.
- Contractor tax number
- TX-409411
- Project
- Government Fibre Backbone — Damascus–Homs Segment
- Contract period
- 2025-06-01 — 2027-01-31
- Original contract value
- SYP2,700,000,000
- Current contract value
- SYP2,700,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 687,750,000 |
| 2 | Less: previous certificates | (443,500,000) |
| 3 | Value of work in this certificate | 244,250,000 |
| 4 | Less: retention (10%) | (24,425,000) |
| 5 | Less: advance payment recovery (10%) | (24,425,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (48,850,000) |
| 8 | Net amount payable to the contractor | SYP195,400,000 |
Amount in words: One hundred ninety-five million four hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 68.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 189,000,000 | 74,525,000 | 36,525,000 | 111,050,000 | 59% |
| Earthworks & foundations | 486,000,000 | 115,100,000 | 58,225,000 | 173,325,000 | 36% |
| Concrete & structural works | 837,000,000 | 150,900,000 | 83,625,000 | 234,525,000 | 28% |
| Mechanical, electrical & plumbing | 648,000,000 | 71,175,000 | 44,375,000 | 115,550,000 | 18% |
| Finishes & external works | 405,000,000 | 27,800,000 | 18,625,000 | 46,425,000 | 11% |
| Testing & commissioning | 135,000,000 | 4,000,000 | 2,875,000 | 6,875,000 | 5% |
| Total | 2,700,000,000 | 443,500,000 | 244,250,000 | 687,750,000 | 25% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Ammar Al-Ahmad
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. George Haddad
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar