Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦5⁩ — February 2026

Government fibre backbone roll-out — Damascus–Homs segment

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
5
Date
⁦2026-03-11⁩
Reference
PAY-2025-020-05

Interim payment certificate no. (⁦5⁩)

For the work of February 2026

Contract number
PSA/2025/020
Tender file no.
2504510654
Contract
Government fibre backbone roll-out — Damascus–Homs segment
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Government Fibre Backbone — Damascus–Homs Segment
Contract period
⁦2025-06-01⁩ — ⁦2027-01-31⁩
Original contract value
SYP2,700,000,000
Current contract value
SYP2,700,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date923,000,000
2Less: previous certificates(687,750,000)
3Value of work in this certificate235,250,000
4Less: retention (⁦10%⁩)(23,525,000)
5Less: advance payment recovery (⁦10%⁩)(23,525,000)
6Less: delay and breach penalties0
7Total deductions(47,050,000)
8Net amount payable to the contractorSYP188,200,000

Amount in words: One hundred eighty-eight million two hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 92.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation189,000,000115,125,00033,925,000149,050,000⁦79%⁩
Earthworks & foundations486,000,000177,975,00054,625,000232,600,000⁦48%⁩
Concrete & structural works837,000,000234,075,00080,675,000314,750,000⁦38%⁩
Mechanical, electrical & plumbing648,000,000110,875,00044,200,000155,075,000⁦24%⁩
Finishes & external works405,000,00043,425,00018,875,00062,300,000⁦15%⁩
Testing & commissioning135,000,0006,275,0002,950,0009,225,000⁦7%⁩
Total2,700,000,000687,750,000235,250,000923,000,000⁦34%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2026-03-11⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-03-13⁩

Project manager

Eng. George Haddad

Haddad⁦2026-03-16⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-03-19⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-03-22⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-03-11⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2026-03-13⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-03-16⁩

    Eng. George Haddad · Director, Data Centres & Government Network

    Took 3 days

  4. Payment order prepared⁦2026-03-19⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-03-22⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-05-02⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. George Haddad → Dr. Samer Al-Daqqar

Certificate history

22 March 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-03-22 13:00

19 March 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-03-19 13:00

16 March 2026

  1. Approval: Eng. George Haddad signed “Project manager certifies”

    2026-03-16 13:00

13 March 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-03-13 13:00

11 March 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-03-11 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close