Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 7
- Date
- 2026-07-08
- Reference
- PAY-2025-020-07
Interim payment certificate no. (7)
For the work of June 2026
- Contract number
- PSA/2025/020
- Tender file no.
- 2504510654
- Contract
- Government fibre backbone roll-out — Damascus–Homs segment
- Contractor
- Modern Networks Telecom Co.
- Contractor tax number
- TX-409411
- Project
- Government Fibre Backbone — Damascus–Homs Segment
- Contract period
- 2025-06-01 — 2027-01-31
- Original contract value
- SYP2,700,000,000
- Current contract value
- SYP2,700,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 1,277,750,000 |
| 2 | Less: previous certificates | (1,108,000,000) |
| 3 | Value of work in this certificate | 169,750,000 |
| 4 | Less: retention (10%) | (16,975,000) |
| 5 | Less: advance payment recovery (10%) | (16,975,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (33,950,000) |
| 8 | Net amount payable to the contractor | SYP135,800,000 |
Amount in words: One hundred thirty-five million eight hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 127.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 189,000,000 | 168,125,000 | 20,875,000 | 189,000,000 | 100% |
| Earthworks & foundations | 486,000,000 | 299,875,000 | 39,475,000 | 339,350,000 | 70% |
| Concrete & structural works | 837,000,000 | 377,350,000 | 58,375,000 | 435,725,000 | 52% |
| Mechanical, electrical & plumbing | 648,000,000 | 180,850,000 | 33,800,000 | 214,650,000 | 33% |
| Finishes & external works | 405,000,000 | 71,400,000 | 14,850,000 | 86,250,000 | 21% |
| Testing & commissioning | 135,000,000 | 10,400,000 | 2,375,000 | 12,775,000 | 9% |
| Total | 2,700,000,000 | 1,108,000,000 | 169,750,000 | 1,277,750,000 | 47% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Ammar Al-Ahmad
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. George Haddad
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar