Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦8⁩ — August 2026

Government fibre backbone roll-out — Damascus–Homs segment

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
8
Date
⁦2026-09-05⁩
Reference
PAY-2025-020-08

Interim payment certificate no. (⁦8⁩)

For the work of August 2026

Contract number
PSA/2025/020
Tender file no.
2504510654
Contract
Government fibre backbone roll-out — Damascus–Homs segment
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Government Fibre Backbone — Damascus–Homs Segment
Contract period
⁦2025-06-01⁩ — ⁦2027-01-31⁩
Original contract value
SYP2,700,000,000
Current contract value
SYP2,700,000,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date1,370,000,000
2Less: previous certificates(1,277,750,000)
3Value of work in this certificate92,250,000
4Less: retention (⁦10%⁩)(9,225,000)
5Less: advance payment recovery (⁦10%⁩)(9,225,000)
6Less: delay and breach penalties0
7Total deductions(18,450,000)
8Net amount payable to the contractorSYP73,800,000

Amount in words: Seventy-three million eight hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 137M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation189,000,000178,675,00010,325,000189,000,000⁦100%⁩
Earthworks & foundations486,000,000355,600,00021,900,000377,500,000⁦78%⁩
Concrete & structural works837,000,000435,450,00031,725,000467,175,000⁦56%⁩
Mechanical, electrical & plumbing648,000,000211,475,00018,675,000230,150,000⁦36%⁩
Finishes & external works405,000,00084,200,0008,275,00092,475,000⁦23%⁩
Testing & commissioning135,000,00012,350,0001,350,00013,700,000⁦10%⁩
Total2,700,000,0001,277,750,00092,250,0001,370,000,000⁦51%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2026-09-05⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-09-07⁩

Project manager

Eng. George Haddad

Haddad⁦2026-09-10⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-09-13⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-09-16⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-09-05⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2026-09-07⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-09-10⁩

    Eng. George Haddad · Director, Data Centres & Government Network

    Took 3 days

  4. Payment order prepared⁦2026-09-13⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-09-16⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-09-19⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. George Haddad → Dr. Samer Al-Daqqar

Certificate history

16 September 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-09-16 13:00

13 September 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-09-13 13:00

10 September 2026

  1. Approval: Eng. George Haddad signed “Project manager certifies”

    2026-09-10 13:00

7 September 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-09-07 13:00

5 September 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-09-05 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close