Certificate ⁦6⁩ — April 2026

Government fibre backbone roll-out — Damascus–Homs segment

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
6
Date
⁦2026-05-09⁩
Reference
PAY-2025-020-06

Interim payment certificate no. (⁦6⁩)

For the work of April 2026

Contract number
PSA/2025/020
Tender file no.
2504510654
Contract
Government fibre backbone roll-out — Damascus–Homs segment
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Government Fibre Backbone — Damascus–Homs Segment
Contract period
⁦2025-06-01⁩ — ⁦2027-01-31⁩
Original contract value
SYP2,700,000,000
Current contract value
SYP2,700,000,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date1,108,000,000
2Less: previous certificates(923,000,000)
3Value of work in this certificate185,000,000
4Less: retention (⁦10%⁩)(18,500,000)
5Less: advance payment recovery (⁦10%⁩)(18,500,000)
6Less: delay and breach penalties0
7Total deductions(37,000,000)
8Net amount payable to the contractorSYP148,000,000

Amount in words: One hundred forty-eight million Syrian pounds only

Retention held up to this certificate: SYP 110.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation189,000,000153,125,00025,800,000178,925,000⁦95%⁩
Earthworks & foundations486,000,000237,300,00041,925,000279,225,000⁦57%⁩
Concrete & structural works837,000,000314,275,00063,550,000377,825,000⁦45%⁩
Mechanical, electrical & plumbing648,000,000150,375,00035,775,000186,150,000⁦29%⁩
Finishes & external works405,000,00059,300,00015,500,00074,800,000⁦18%⁩
Testing & commissioning135,000,0008,625,0002,450,00011,075,000⁦8%⁩
Total2,700,000,000923,000,000185,000,0001,108,000,000⁦41%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2026-05-09⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-05-11⁩

Project manager

Eng. George Haddad

Haddad⁦2026-05-14⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-05-17⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-05-20⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-05-09⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2026-05-11⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-05-14⁩

    Eng. George Haddad · Director, Data Centres & Government Network

    Took 3 days

  4. Payment order prepared⁦2026-05-17⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-05-20⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-09-19⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. George Haddad → Dr. Samer Al-Daqqar

Certificate history

20 May 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-05-20 13:00

17 May 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-05-17 13:00

14 May 2026

  1. Approval: Eng. George Haddad signed “Project manager certifies”

    2026-05-14 13:00

11 May 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-05-11 13:00

9 May 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-05-09 09:00