Certificate ⁦3⁩ — October 2025

Government fibre backbone roll-out — Damascus–Homs segment

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
3
Date
⁦2025-11-12⁩
Reference
PAY-2025-020-03

Interim payment certificate no. (⁦3⁩)

For the work of October 2025

Contract number
PSA/2025/020
Tender file no.
2504510654
Contract
Government fibre backbone roll-out — Damascus–Homs segment
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Government Fibre Backbone — Damascus–Homs Segment
Contract period
⁦2025-06-01⁩ — ⁦2027-01-31⁩
Original contract value
SYP2,700,000,000
Current contract value
SYP2,700,000,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SYP)

1Total value of work completed to date443,500,000
2Less: previous certificates(261,000,000)
3Value of work in this certificate182,500,000
4Less: retention (⁦10%⁩)(18,250,000)
5Less: advance payment recovery (⁦10%⁩)(18,250,000)
6Less: delay and breach penalties0
7Total deductions(36,500,000)
8Net amount payable to the contractorSYP146,000,000

Amount in words: One hundred forty-six million Syrian pounds only

Retention held up to this certificate: SYP 44.4M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation189,000,00043,475,00028,200,00071,675,000⁦38%⁩
Earthworks & foundations486,000,00067,250,00044,500,000111,750,000⁦23%⁩
Concrete & structural works837,000,00088,850,00062,375,000151,225,000⁦18%⁩
Mechanical, electrical & plumbing648,000,00042,350,00032,150,00074,500,000⁦11%⁩
Finishes & external works405,000,00016,650,00013,275,00029,925,000⁦7%⁩
Testing & commissioning135,000,0002,425,0002,000,0004,425,000⁦3%⁩
Total2,700,000,000261,000,000182,500,000443,500,000⁦16%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2025-11-12⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-11-14⁩

Project manager

Eng. George Haddad

Haddad⁦2025-11-17⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-11-20⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-11-23⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-11-12⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2025-11-14⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-11-17⁩

    Eng. George Haddad · Director, Data Centres & Government Network

    Took 3 days

  4. Payment order prepared⁦2025-11-20⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-11-23⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-11-19⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-05-19⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. George Haddad → Dr. Samer Al-Daqqar

Certificate history

23 November 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-11-23 13:00

20 November 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-11-20 13:00

17 November 2025

  1. Approval: Eng. George Haddad signed “Project manager certifies”

    2025-11-17 13:00

14 November 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-11-14 13:00

12 November 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-11-12 09:00