Government Fibre Backbone — Damascus–Homs Segment
Add to watchlistLaying a government fibre backbone between Damascus and Homs that links the ministries’ directorates and the main and backup data centres — the first segment of the network that will reach every governorate.
Budget (BAC)
Actual cost
57% of budget
Progress
Estimate at completion
+SYP 102.1M
SPI · CPI
Forecast finish
33 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure12 December 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-09-18 | 2025-12-08 | +81 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-27 | 2026-05-19 | +143 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-05-26 | 2026-11-11 | +169 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-10-23 | 2027-01-16 | +85 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-01-31 | 2027-03-01 | +29 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
55%Awaiting acceptance
10%Not handed in
35%Deliverable flow
Display options
| Project plan & baseline018-D1 | 4% | CRT-018-01 | Approved | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Eng. Mazen Kassab | 2025-07-30 | V1 | 3 of 3 |
| Monitoring & reporting018-D2 | 4% | CRT-018-02 | Approved | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2025-09-18 | V1 | 3 of 3 |
| Detailed design018-D3 | 8% | CRT-018-03 | Approved | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2025-11-07 | V1 | 3 of 3 |
| Permits & approvals018-D4 | 7% | CRT-018-04 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mazen Kassab | 2025-12-27 | V1 | 3 of 3 |
| Site works & excavation018-D5 | 16% | CRT-018-05 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mazen Kassab | 2026-02-15 | V1 | 3 of 3 |
| Structure018-D6 | 16% | CRT-018-06 | Approved | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Eng. Mazen Kassab | 2026-04-06 | V1 | 3 of 3 |
| Finishes018-D7 | 10% | — | Under review | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2026-05-26 | V1 | 1 of 3 |
| Supply018-D8 | 8% | — | Draft | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Eng. Mazen Kassab | 2026-07-15 | V0 | 0 of 3 |
| Installation018-D9 | 8% | — | Draft | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2026-09-03 | V0 | 0 of 3 |
| Testing & commissioning018-D10 | 8% | — | Draft | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mazen Kassab | 2026-10-23 | V0 | 0 of 3 |
| Provisional acceptance018-D11 | 6% | — | Draft | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2026-12-12 | V0 | 0 of 3 |
| Final acceptance018-D12 | 5% | — | Draft | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mazen Kassab | 2027-01-31 | V0 | 0 of 3 |
| Total · 12 | 100% |