O-5 · Authority level
Hospitals and schools back in service sooner
School and hospital rehabilitation is going well; we want clearer impact: open classrooms and working beds in the governorates people are returning to.
- Progress
- 31%
- Key results done
- 0 / 3
- Average confidence
- 7.7
- Cycle
- Q4 2026
Expected by today 30%
Of the objective’s key results
Of 10
2026-10-01 → 2026-12-31
KR-05.1Reach 220 schools rehabilitated and equipped since the plan began
- Start
- 165 schools
- Current
- 185 schools
- Target
- 220 schools
Planned to date 30%
The result since the cycle began
schools
Check-ins (2)
2026-10-15 · Mariam Al-Zoubi
8highThe owner’s confidence of reaching the target by the end of the cycle: 8 of 10. 7 and above is high, 4 to 6 medium, 3 and below low.185 schools
2026-10-01 · Mariam Al-Zoubi
8highThe owner’s confidence of reaching the target by the end of the cycle: 8 of 10. 7 and above is high, 4 to 6 medium, 3 and below low.172 schools
KR-05.2Rehabilitate 900 classrooms in Aleppo, Idlib and Raqqa schools
- Start
- 0 classrooms
- Current
- 260 classrooms
- Target
- 900 classrooms
Planned to date 30%
The result since the cycle began
classrooms
Check-ins (2)
2026-10-15 · Eng. Fadi Al-Droubi
7highThe owner’s confidence of reaching the target by the end of the cycle: 7 of 10. 7 and above is high, 4 to 6 medium, 3 and below low.260 classrooms
2026-10-01 · Eng. Fadi Al-Droubi
7highThe owner’s confidence of reaching the target by the end of the cycle: 7 of 10. 7 and above is high, 4 to 6 medium, 3 and below low.90 classrooms
KR-05.3Reach 2,400 rehabilitated beds in public hospitals
- Start
- 1,580 beds
- Current
- 1,810 beds
- Target
- 2,400 beds
Planned to date 30%
The result since the cycle began
beds
Check-ins (2)
2026-10-15 · Eng. Fadi Al-Droubi
8highThe owner’s confidence of reaching the target by the end of the cycle: 8 of 10. 7 and above is high, 4 to 6 medium, 3 and below low.1,810 beds
2026-10-01 · Eng. Fadi Al-Droubi
8highThe owner’s confidence of reaching the target by the end of the cycle: 8 of 10. 7 and above is high, 4 to 6 medium, 3 and below low.1,650 beds