PRJ-2026-029On track3PlanningWaterfallNot startedDelivered by:Ministry of Education

e-Learning Platform & Computer Labs for Raqqa Schools

Add to watchlist

Computer labs in 30 schools in Raqqa city and an e-learning platform with the national curriculum, plus teacher training.

Budget (BAC)

SYP 187.5M

Actual cost

SYP 7.5M

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 187.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2026-02-23⁩
ApprovedDMD-2026-006e-Learning platform & computer labs for Raqqa schools

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-029
Project
e-Learning Platform & Computer Labs for Raqqa Schools
Portfolio
Planning, Statistics & Capability Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Eng. Abdulrahman Al-Kilani
Project manager
Mariam Al-Zoubi

1The proposalAuto-filled

TitleAuto-filled
e-Learning platform & computer labs for Raqqa schools
Proposed byAuto-filled
Muhannad Al-Homsi
DepartmentAuto-filled
General Directorate of Human Resources & Administrative Development
Submitted onAuto-filled
⁦2026-02-23⁩
Proposal numberAuto-filled
DMD-2026-006

2Justification

The problem or need

Raqqa’s schools lack computer labs and digital learning content, and 72% of teachers have had no e-learning training.

Today

One working lab for every nine schools, no shared learning platform and no tracking of pupils’ attainment.

3Objectives

  1. An e-learning platform and computer labs in 60 schools serving 30,000 pupils, with 900 teachers trained through an accredited training partner.

Strategic objectives served

  • SO-3.2 — Develop human capital in public bodies

4Expected benefits

KindBenefit
Productivity900 teachers trained in e-learning
Cost savingBooks and printing cost down SYP 60M a year

5Cost & feasibilityAuto-filled

Estimated cost

SYP 187.5M

Net present value

SYP 44.5M

Return on investment

⁦31%⁩

Payback

3.7 years

YearCapexOpexBenefit
2026SYP 112.5MSYP 0SYP 0
2027SYP 75MSYP 20MSYP 40M
2028SYP 0SYP 20MSYP 72.5M
2029SYP 0SYP 21.3MSYP 85M
2030SYP 0SYP 21.3MSYP 90M
2031SYP 0SYP 22.5MSYP 95M

6Initial risks

RiskLevelProposed response
Late teacher nominationsMediumApproved quotas per school

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Muhannad Al-HomsiDirector General, Human Resources & Administrative DevelopmentSubmitted—⁦2026-02-23⁩ 13:34
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2026-02-24⁩ 11:14
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-02-25⁩ 12:21
4Portfolio manager reviewTechnical acceptanceDr. Reem Al-QabbaniPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2026-03-01⁩ 13:28
5Cost & funding reviewFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-03-04⁩ 13:10
6Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2026-03-08⁩ 09:42

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2026-02-24⁩

PMO review

Mariam Al-Zoubi

Approved⁦2026-02-25⁩

Portfolio manager review

Dr. Reem Al-Qabbani

Approved⁦2026-03-01⁩

Cost & funding review

Rasha Al-Mudarres

Approved⁦2026-03-04⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2026-03-08⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Muhannad Al-Homsi on ⁦2026-02-23⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2026-02-24⁩ at ⁦11:14⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-02-25⁩ at ⁦12:21⁩

  3. Technical acceptance

    Portfolio manager review

    Dr. Reem Al-Qabbani · Portfolio manager

    Approved · ⁦2026-03-01⁩ at ⁦13:28⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-03-04⁩ at ⁦13:10⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2026-03-08⁩ at ⁦09:42⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-03-16⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Muhannad Al-Homsi

  2. V1Returned for edit⁦2026-02-23⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Muhannad Al-Homsi

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close