PRJ-2026-023On track2InitiationAgileNot startedDelivered by:Planning and Statistics Authority

Medium-Term Plan Implementation Tracker (ministries & governorates)

Add to watchlist

A system that follows each ministry’s and governorate’s delivery of the 2026–2028 medium-term plan and the steering committee’s recommendations, with progress indicators and delay alerts.

Budget (BAC)

SYP 700M

Actual cost

SYP 7M

⁦1%⁩ of budget

Progress

⁦1%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 700M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

InitiationStage ⁦2⁩ of ⁦5⁩

Next gate:Planning6 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current stageInitiation · Current stage
  3. Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
  4. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
PSA-PMO-F04
Template edition
3.0
Version
V1
Form date
⁦2026-10-19⁩
In approvalPRJ-2026-023Medium-Term Plan Implementation Tracker (ministries & governorates)

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-023
Project
Medium-Term Plan Implementation Tracker (ministries & governorates)
Portfolio
Digital Government Services & Data Portfolio
Sector
Economic & Social Planning Sector
Sponsor
Eng. Mustafa Al-Awa
Project manager
Razan Al-Rifai

1Objective

Background

A system that follows each ministry’s and governorate’s delivery of the 2026–2028 medium-term plan and the steering committee’s recommendations, with progress indicators and delay alerts.

Project objectives

  1. Governorate plans and a balanced share of public investment
  2. Sound governance and effective follow-up of projects and data

2Scope

In scope

  • A system that follows each ministry’s and governorate’s delivery of the 2026–2028 medium-term plan and the steering committee’s recommendations, with progress indicators and delay alerts.
  • Identity checks against the civil registry
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2026-09-25⁩
Main deliverable — stage 1⁦2027-05-10⁩
Main deliverable — final stage⁦2027-10-25⁩
Final report⁦2027-12-31⁩
MilestoneDate
Charter approved⁦2026-09-04⁩
Contract signed⁦2026-11-22⁩
50% of works complete⁦2027-05-10⁩
Provisional acceptance⁦2027-11-23⁩
Closure⁦2027-12-31⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Mustafa Al-Awa
Project ownerAuto-filled
Iman Al-Jasem
Project managerAuto-filled
Razan Al-Rifai
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
National Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSYP 505M
Supervision & consultingSYP 97.5M
Internal teamSYP 62.5M
Contingency reserve (5%)SYP 35M
Approved budgetSYP 700M

Funding

The delivering body’s investment-plan allocations

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the unified contracts law (Law 51 of 2004)

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Razan Al-RifaiDirector, Data & AISubmitted—⁦2026-10-19⁩ 10:00
2PMO complianceMethodology reviewApproval enginePMO — directorPre-breach alert—⁦2026-10-22⁩ 08:00
3PMO complianceMethodology reviewApproval engineEscalated automatically to Senior management (Dr. Samer Al-Daqqar) on ⁦2026-10-27⁩Automatic escalation—⁦2026-10-27⁩ 08:05

Signatures

PMO compliance

Dr. Reem Al-Qabbani

Awaiting decision

Project owner

Iman Al-Jasem

Later

Budget funding confirmed

Rasha Al-Mudarres

Later

Sponsor approval

Eng. Mustafa Al-Awa

Later

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F04 · version V1

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Razan Al-Rifai on ⁦2026-10-19⁩

  1. Methodology review

    PMO compliance

    Dr. Reem Al-Qabbani · PMO — director
    4 working days overdueAction time limit exceeded · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-22⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-22⁩

    Escalated automatically to Senior management (Dr. Samer Al-Daqqar) on ⁦2026-10-27⁩

  2. Technical acceptance

    Project owner

    Iman Al-Jasem · Project owner

    Limit 3 working days · Expected by ⁦2026-10-27⁩

  3. Financial approval

    Budget funding confirmed

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Delegated to Omar Al-Nahhas

    Limit 2 working days · Expected by ⁦2026-10-29⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Mustafa Al-Awa · Project sponsor

    Limit 3 working days · Expected by ⁦2026-11-03⁩

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-10-19⁩

    Submitted for approval

    • First complete version

    Razan Al-Rifai

Only one version so far.