PRJ-2026-023On track2InitiationAgileNot startedDelivered by:Planning and Statistics Authority

Medium-Term Plan Implementation Tracker (ministries & governorates)

Add to watchlist

A system that follows each ministry’s and governorate’s delivery of the 2026–2028 medium-term plan and the steering committee’s recommendations, with progress indicators and delay alerts.

Budget (BAC)

SYP 700M

Actual cost

SYP 7M

⁦1%⁩ of budget

Progress

⁦1%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 700M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

InitiationStage ⁦2⁩ of ⁦5⁩

Next gate:Planning6 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current stageInitiation · Current stage
  3. Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
  4. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Priority evaluation

Criteria, weights and the P1–P4 result

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

Form no.
PSA-PMO-F02
Template edition
1.3
Version
V4
Form date
⁦2026-02-18⁩
ApprovedDMD-2026-003Medium-term plan implementation tracker

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-023
Project
Medium-Term Plan Implementation Tracker (ministries & governorates)
Portfolio
Digital Government Services & Data Portfolio
Sector
Economic & Social Planning Sector
Sponsor
Eng. Mustafa Al-Awa
Project manager
Razan Al-Rifai

1The resultAuto-filled

Priority score

82 of 100

Class

P1

75–100

Priority model

Version 4

Class thresholdsAuto-filled

P1 from 75 · P2 from 60 · P3 from 45 · P4 below 45

2Criteria and weightsAuto-filled

Rated 1–5; the cost criteria (risk, complexity, resources) are turned around before weighting.

CriterionWeightRatingPoints
Fit with the development framework⁦20%⁩5.020.0
Development value⁦12%⁩5.012.0
Economic & social return⁦8%⁩5.08.0
Urgency⁦10%⁩4.89.5
Legal requirement⁦10%⁩1.41.0
Risk⁦7%⁩1.36.5
Complexity⁦6%⁩2.24.2
Resource requirement⁦5%⁩1.34.6
Impact on citizens & beneficiaries⁦14%⁩3.910.2
Sustainability impact⁦3%⁩1.80.6
Digital transformation impact⁦5%⁩5.05.0
Total⁦100%⁩—82

Approval logChain: Priority evaluation approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Mariam Al-ZoubiDirector, Education & Rural Development ProjectsSubmitted—⁦2026-02-18⁩ 14:17
2Evaluation checked against the modelMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-02-22⁩ 12:51
3Portfolio manager reviewTechnical acceptanceBasel Al-MahayniPortfolio managerApproved—⁦2026-02-23⁩ 13:58
4Class approved — Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2026-02-24⁩ 14:05

Signatures

Evaluation checked against the model

Mariam Al-Zoubi

Approved⁦2026-02-22⁩

Portfolio manager review

Basel Al-Mahayni

Approved⁦2026-02-23⁩

Class approved — Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2026-02-24⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F02 · version V4

Priority evaluation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Priority evaluation approval · version ⁦1⁩

Submitted by Mariam Al-Zoubi on ⁦2026-02-18⁩

  1. Methodology review

    Evaluation checked against the model

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-02-22⁩ at ⁦12:51⁩

  2. Technical acceptance

    Portfolio manager review

    Basel Al-Mahayni · Portfolio manager

    Approved · ⁦2026-02-23⁩ at ⁦13:58⁩

  3. Technical acceptance

    Class approved — Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2026-02-24⁩ at ⁦14:05⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V4ApprovedCurrent⁦2026-02-18⁩

    Evaluated on the approved priority model

    Mariam Al-Zoubi

Only one version so far.